SEVEN-G
Document 21 · 01-10-2026

Document 21 · Gate and audit criteria

Gate and audit criteria

What must be met at each decision gate, how it is verified and how it is audited

Fernando García VarelaVersion 0.3 (working draft)01-10-2026Draft for review
8decision gates
128coded criteria
4sign-offs with veto at G5
3audit outcomes

01Purpose and scope

This document sets out the criteria that must be met to pass each decision gate of the SEVEN-G lifecycle (G0, G1, G2, G3, G4, G5, R6 and G7), the rules for verifying evidence, the calculation of the degree of compliance, the multi-level go-live sign-off and the criteria used to audit that the gates have been applied correctly.

It develops section 7 of document 01 (Foundational methodology) and may not contradict it. The checklists in document 22 turn each criterion in this document into a binary control with the same code.

Applies to How
In-house AI use cases All applicable criteria according to intensity, ambition and technology.
Third-party AI integrated into processes All criteria; those marked [TER] are added, and those relating to design and construction are read as selection, integration, contract and supplier controls.
Corporate use of general-purpose AI Only if it meets any Enterprise criterion (01 §9.2); otherwise it is governed through the inventory, policy and technical controls.
Systems in production prior to the adoption of the framework Review equivalent to G7 (01 §14) with the G7 criteria, supplemented by the criteria marked ◆ in G4, G5 and R6 that are applicable.

This document does not constitute legal advice. The regulatory references were consulted in September 2026; the application dates of some obligations under the EU AI Act have been the subject of amendment proposals, so their applicability must be verified in each case.


02How to read the criteria

2.1 Table columns

Column Content
Code G<n>.<nn> for the gates and R6.<nn> for the continuity review. It is the same code used by document 22, the gate manager (T03) and the decision record (P29). A code is not reused even if the criterion is withdrawn.
Criterion Verifiable condition. The initial tags delimit its scope (section 2.3).
Evidence Template (P01–P31) or tool (T01–T22) where the proof must be found.
Mandatory Nature of the criterion (section 2.2).
Lite · Enterprise Whether it applies at each intensity (Express intensity has no column of its own: its list is set by the rule in section 2.5): Yes (in full), Simpl. (with a simplified template), Rec. (recommended at that intensity) or — (not applicable at that intensity).
Optimise / Augment / Transform How the criterion changes according to the ambition level. "—" indicates that it does not change.

2.2 Mandatory nature

Value Meaning Effect on the decision
Yes Mandatory and not conditionable. Must be Met (or justified Not applicable) to Proceed or Proceed with conditions.
Yes ◆ Mandatory, not conditionable and also a critical control for security, legal compliance or human oversight (01 §7.3). Same as Yes. It is never accepted as a condition. At Enterprise G5 it grounds the veto. Its absence in a system in production is a major or critical nonconformity.
Conditionable Mandatory. If it is not fully met, the shortfall is not critical and the evidence exists, it allows Proceed with conditions. The condition carries a time limit, an owner and a means of verification, and is checked at the latest at the next gate.
Recommended "Should" (01 §1.3). May be omitted with a recorded justification. It does not block. Omitting it without justification is an audit observation.

2.3 Scope tags

Tag Applies when If it does not apply
[GEN] The registered technology is Generative AI or Agent. Not applicable, justified by the technology tag in the register.
[AG] The system executes actions or prepares them for human validation (autonomy A1, A2 or A3). Section 8.2 indicates what each level requires. Not applicable, justified by the approved autonomy level (A0).
[TER] An AI supplier is involved: model, platform or software with AI functions. Not applicable, justified by the suppliers field in the register.
Transform / Scale / Retire / Iterate Only for that ambition level or for that proposed outcome. Not applicable without further justification.

2.4 Status of each criterion

Each criterion is recorded in T03 with one of the four statuses in document 03 §3.4: Met · Not met · Not applicable · Pending. Not applicable requires a justification, which the verifier validates; an unjustified Not applicable is treated as Not met.

2.5 Criteria at Express intensity

At Express intensity (01 §9.4) each gate is assessed with a reduced list that is not decided case by case but with a fixed rule:

  1. All "Yes ◆" criteria that apply to the use case's profile (security, legal compliance, human oversight): N-08 prevents them from being treated as conditions, so they cannot disappear either.
  2. The criteria that sustain the core (01 §14.1): G0.01, G0.05, G0.06, G0.07, G0.08 and G0.09 (record, roles, incompatibilities, intensity, register and no budget before the decision); G1.01 and G1.03 (business need and non-AI alternative); G2.01, G2.03, G2.04, G2.06 and G2.08 (falsifiable hypothesis with baseline, target, value with formula and stop criterion); G3.06, G3.11 and G3.13 (stop criteria in force, risks assessed and plan for High risks); G5.09, G5.11, G5.19 and G5.22 (stop criterion not reached, tested rollback, literacy and conditions closed).
  3. R6 and G7: the same criteria as in Lite.

The other criteria appear in the decision as Not applicable, with the justification "Does not apply at Express intensity (document 21, section 2.5)". Criteria tagged [GEN], [AG] or [TER] follow section 2.3. The gate manager's catalogue carries this list in its Express column. In the typical use case of the improvement plan's baseline (an internal generative assistant from an approved supplier), the reduced list goes from 90 to 47 criteria, of which 27 are "Yes ◆".


03Rules common to all gates

3.1 Dual validation

A criterion is only Met if both conditions in 01 §7.2 are satisfied at the same time, and the verifier records them separately:

Dimension Question Example of failure
R · Result Do the actual data, tests or results demonstrate what the criterion requires? The hypothesis canvas is complete, but the baseline has not been measured.
D · Documentation Does the evidence exist, is it valid (section 4) and has it been verified? The pilot reached the threshold, but there is no dated report or version of the results.

Results without documentation, or documentation without results, leave the criterion Not met or Pending.

3.2 Decision rules

The seven rules in 01 §7.4 apply, with these operational clarifications:

  1. Segregation of duties. The author of a piece of evidence does not verify it or decide on it. The verifier does not decide. If the decision-maker provided evidence, they must abstain, and the substitute provided for in the governance model (document 30) decides.
  2. No evidence, no decision. If the verification concludes Nonconformant (section 10.2), the request goes back to the team and does not reach the deciding body.
  3. Prior existence. All evidence must be dated before the gate request. Corrections requested by the verifier generate a new version before the decision.
  4. Conditions. Only on Conditionable criteria. Each condition has a time limit, an owner, a linked criterion and a means of verification. An expired condition turns the outcome into Iterate.
  5. Iterations. After two iterations at the same gate, the third decision is taken by the higher body defined in document 30.
  6. Stop criteria. They are not relaxed without the approval of the body that authorised the use case, recorded before the affected decision.
  7. Record. Every decision is documented in P29 and generates the corresponding events in T01.

3.3 Meeting the criteria is necessary, not sufficient

All criteria being Met allows Proceed, but does not require it. The competent body may decide to Iterate, Pivot or Stop with a recorded reason (for example, a change in strategic priority). Conversely, no body may record Proceed with a Yes or Yes ◆ criterion that is Not met or Pending.

3.4 Grouped gates in Lite

At Lite and Express intensity, G0, G1 and G2 may be resolved in a single session, as may G4 and G5 (01 §7.5). G3 is always separate; at Express it may be resolved in writing, without a session, with the risk clearance recorded (01 §9.4). Grouping does not merge criteria: each gate keeps its own list, its status per criterion and its section in P29, and each piece of evidence is verified.

3.5 Board decisions in Transform

Transform use cases are always Enterprise (01 §9.2) and require express approval by the board or its board committee at G2 (authorisation of the bet, criterion G2.12) and at G7 when the decision is to scale (criterion G7.09). The approval is recorded in P29 with a reference to the minutes or to the register of recommendations and decisions (document 62).


04Valid evidence

4.1 Rules

A piece of evidence is valid if it passes the following fourteen rules. Document 22 turns them into the cross-cutting checklist LV-EV, with the same codes.

Code Rule What is checked If not met
EV.01 Identification Use case code, template (P) or source record, and title. Pending
EV.02 Author Person and role who prepares it. Pending
EV.03 Date Date of preparation and of last modification. Pending
EV.04 Version Version number; the verified version is the one linked in P29. A subsequent change requires new verification. Pending
EV.05 Prior existence Dated before the gate request, and the activity described predates the decision. Documentation prepared after the fact to justify progress already made invalidates the gate (01 §7.4). Not valid · major nonconformity
EV.06 Integrity and traceability Stored in the document repository with version history; link accessible to the verifier and the auditor from T01 or T03. Pending
EV.07 Relevance It refers to this use case, its scope and the system version. Reuse of evidence from another use case is justified. Not valid
EV.08 Real data Where the criterion requires results: reproducible source, period and method; amounts with a formula and status (validated, declared or estimated). Not valid
EV.09 Approval and segregation Approved by the appropriate person; author, verifier and decision-maker are different people. Not valid · major nonconformity if there is self-approval
EV.10 Completeness Mandatory fields of the template filled in or covered by referenced evidence (section 4.3); in Lite, those not marked (Enterprise). Missing data are shown as "no data", not as zero. Pending
EV.11 Consistency Figures and statements match across evidence (for example, value in P08, P10 and P28; risks in P12 and controls in P18). Not met until clarified
EV.12 Information protection It contains no unnecessary personal data; access restricted according to its classification. Observation or nonconformity, depending on the case
EV.13 System-generated evidence Dated export or time-stamped link to logs, dashboards or test results. A screenshot with no date or source is not valid. Not valid
EV.14 Third-party evidence Identifiable issuer, validity and a scope that covers the contracted service (reports, certifications, supplier documentation). Not valid

4.2 Evidence accepted with shortfalls

The verifier may accept a piece of evidence with minor shortfalls (rules EV.01–EV.04, EV.06 or EV.10) only if they do not affect a Yes or Yes ◆ criterion and are corrected before the decision. Rules EV.05 and EV.09 admit no exception.

4.3 Reference rather than reproduce

A large company already has mechanisms that produce much of what SEVEN-G asks for: business cases, impact assessments, supplier assessments, contracts, architecture and change records, continuity plans, financial controls. Evidence the company already has meets the criterion if it covers what is required, without copying it into a template (principle 11 in 01 §3, proportionality). The SEVEN-G template then serves as a checklist of what the evidence must contain, not as a document to fill in.

A piece of referenced evidence is valid if it meets the same rules EV.01–EV.14 as any other and, in addition:

Requirement What is checked
Locatable reference Source system or repository, identifier or link, version and date, so that the verifier and the auditor can find it without asking for it (EV.06). In T01 it is recorded with origin "reference" and its source system.
Owner Person and role who prepared or approved it in its source process (EV.02). Segregation of duties is checked in the same way (EV.09).
Coverage The verifier compares the evidence with the template it covers and notes what is missing. What is missing is completed in a short annex with only those fields, never by copying what is already there.
Validity and relevance It refers to this use case, its scope and the system version (EV.07); if it is updated in its source process, it is verified again (EV.04).

Usual equivalences (indicative; each company sets them when implementing the framework, document 90):

Evidence the company usually has SEVEN-G template it can cover What is usually missing and goes into the annex
Business case from the investment committee P08, P10 Falsifiable hypothesis, stop criteria and status of each amount (estimated, declared, validated)
Management control baseline P09 Measurement method and period
Data protection impact assessment P47 (and its part of P11) AI-specific risks: bias, explainability, human oversight
Procurement third-party risk assessment P14, P55 Use of data for training, location, foundation models and exit (document 36)
The company's contract or standard clauses P56 AI-specific clauses that are missing
Architecture record or design sheet P15 Traceability of inputs, outputs and model versions
Security design and threat analysis P18 AI-specific threats: prompt injection, poisoning, leakage
Change management and release to production P21, P23 Risk clearance signature or multi-level sign-off
Continuity plan and rollback procedure P19 Rollback test with its actual time
Training and change communication plan P20 AI literacy and usage measurement
Operations manual and incident procedure P24, P26 S1–S4 severities and AI-specific notifications
Benefits tracking by the project office P62 Realisation curve and business owner of the benefit

No evidence is requested twice: if a piece of data is already in referenced evidence, the template refers to it and does not repeat it.

Why it matters. If every use case requires copying into the framework's own templates what the company already has, SEVEN-G becomes a parallel document system that nobody maintains and that drifts away from real processes. Referencing turns the framework into an orchestration and traceability layer over existing processes: the verifier checks what exists where it is, and the template only points out what is missing.


05Degree of compliance and decision rule

5.1 Calculation

Indicator Formula Use
Applicable criteria Total criteria for the gate − criteria that are justified Not applicable. Basis for the calculation.
Degree of compliance Criteria Met ÷ applicable criteria × 100. Indicator in the register and in the funnel metrics (03 §3.5).
Blocking criteria Yes or Yes ◆ criteria that are Not met or Pending. If greater than zero, neither Proceed nor Proceed with conditions is possible.
Open conditionable criteria Conditionable criteria that are Not met or Pending. If greater than zero and there are no blocking criteria, at most Proceed with conditions is possible.
Omitted recommended criteria Recommended criteria not met, with or without justification. Without justification, they give rise to an observation.

The degree of compliance is informative: no percentage threshold allows a gate to be passed with blocking criteria.

Illustrative example (fictitious data): Enterprise G3 with no supplier and no generative AI: 22 criteria, 6 not applicable, 16 applicable. 14 are met; G3.14 is Pending and G3.10 is Not met, both Conditionable. Degree: 87.5%. No blocking criteria: at most, Proceed with conditions verifiable at G4.

5.2 From the status of the criteria to the outcome

From the status of the criteria to the possible outcome
The body decides within what the criteria allow
flowchart TD
  V{"Verification of evidence"} -->|"Nonconformant"| R["Goes back to the team without a decision"]
  V -->|"Conformant or with observations"| B{"Are there blocking criteria?"}
  B -->|"Yes"| X["Only Iterate, Pivot or Stop"]
  B -->|"No"| C{"Are there open conditionable criteria?"}
  C -->|"Yes"| CC["At most Proceed with conditions"]
  C -->|"No"| OK["Proceed allowed"]
  classDef ok fill:#d9ebe0,stroke:#0d7680,color:#1a1817
  classDef med fill:#f2dfce,stroke:#0f5499,color:#1a1817
  classDef ko fill:#f3d3da,stroke:#990f3d,color:#1a1817
  class OK ok
  class CC,R med
  class X ko
Source: SEVEN-G

5.3 Outcomes allowed per gate

Gate Allowed outcomes Mandatory outcomes
Authorisation (G0) Proceed · Proceed with conditions · Iterate · Stop —
G1, G2, G3 Proceed · Proceed with conditions · Iterate · Pivot · Stop G3: Stop if there is a prohibited practice (G3.08).
G4, G5 Proceed · Proceed with conditions · Iterate · Stop G5: no proceeding with a veto in force (section 9).
Continuity review (R6) Proceed with operation · Proceed with conditions · Bring G7 forward Bring G7 forward if any deviation in section 6.7 occurs.
Scale or retire (G7) Scale · Iterate · Retire —

At R6, the immediate suspension of a system is not an outcome of the review: it is triggered at any time by the incident or nonconformity process (document 37). At G7, keeping the system in operation without changes is recorded as Iterate, with a return to phase 6 and the date of the next R6.


06Criteria per gate

Each gate includes its purpose, who verifies and who decides (01 §7.5), the evidence examined and the table of criteria. The ambition column develops 01 §7.6; section 7 summarises it.

6.1 Authorisation (G0)

Purpose. Formally authorise the use case and set the framework within which it will be developed. Without an approved G0 the use case is not authorised: it may not consume budget or access production data.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor AI Committee

Evidence: P01 · P02 · P03 · P04 · P05 · record in T01. Decision: P29.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G0.01 The charter defines the business problem or objective, the scope, the budget for phases 1 to 3 and the signed commitment of the sponsor. P01 Yes Simpl. Yes Transform: senior management sponsor.
G0.02 The use case fits the AI thesis and the portfolio approved in C2 and C3, with a reference to the sphere and the priority assigned. P01 Conditionable Yes Yes Transform: it appears in the portfolio with a board decision expected at G2.
G0.03 The context statement sets out the regulatory (including sector-specific), ethical, data, budgetary and time constraints. P02 Conditionable Simpl. Yes —
G0.04 The preliminary screening rules out the use case pursuing a practice prohibited by applicable regulation. P02 Yes ◆ Yes Yes —
G0.05 The roles are assigned by name: in Lite, at least sponsor, product, technical and risk (operations, at the latest, at G4); in Enterprise, the six roles in 01 §8.1. P03 Yes Yes Yes —
G0.06 The assignment respects the incompatibilities in 01 §8.2 and the AI auditor does not report hierarchically to the sponsor. P03 Yes Yes Yes —
G0.07 The intensity is determined with the eight Enterprise criteria in 01 §9.2, with a justified answer to each one. P04 · T04 Yes Yes Yes Transform: always Enterprise.
G0.08 The use case is registered in the register with code IA-AAAA-NNN, and the planned systems appear in the inventory with technology, exposure and supplier. P05 · T01 · T02 Yes Yes Yes —
G0.09 No construction budget has been consumed and no production data have been accessed before the decision. P01 · T01 Yes Yes Yes —
G0.10 If personal data are expected to be processed, the data protection function has been informed. P02 Conditionable Rec. Yes —

Specific rules. A breach of G0.09 detected after G0 is a major nonconformity and, if production personal data were accessed without a legal basis, it is assessed as critical. G0.04 in Not met leads to Stop.

6.2 Opportunity (G1)

Purpose. Confirm that there is a business opportunity that requires AI and that its potential value justifies formulating a hypothesis.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor Sponsor, informing the committee

Evidence: P06 · P07 · P31 · P04 (if revised). Decision: P29.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G1.01 The opportunity arises from a specific business need: affected process or decision, responsible area and described problem. P06 Yes Yes Yes —
G1.02 The use case sheet explains what it is and what it is used for in language understandable to a non-specialist. P31 Conditionable Simpl. Yes —
G1.03 Non-AI alternatives have been analysed and it is justified what AI provides that those alternatives do not. P06 Yes Yes Yes —
G1.04 The screening notes record the discarded opportunities and the reason. P06 Conditionable Simpl. Yes —
G1.05 The potential value is estimated as an order of magnitude, with explicit assumptions and "estimated" status. P06 Conditionable Yes Yes —
G1.06 The sphere and the ambition level are proposed using the five questions of the classifier. P07 · T05 Yes Yes Yes Transform: the proposal is communicated to the AI Committee before phase 2 begins.
G1.07 The screening of the specific opportunity rules out prohibited practices, and the intensity has been reviewed if decisions about people, specially protected data or direct exposure have emerged. P07 · P04 Yes ◆ Yes Yes —
G1.08 It has been checked on a preliminary basis that the necessary data exist, who owns them and that their use is plausibly lawful. P06 Conditionable Yes Yes —
G1.09 [TER] If buying or partnering is envisaged, the supplier option and a preliminary requirement level (N1–N3) are identified. P06 Conditionable Rec. Yes —
G1.10 The affected roles and teams are identified in order to anticipate the impact on people. P06 Conditionable Yes Yes Optimise: recommended.

Specific rules. Pivot at G1 leads to formulating a different hypothesis in phase 2 while keeping the context approved at G0.

6.3 Hypothesis (G2)

Purpose. Approve a measurable and falsifiable value hypothesis, with a baseline, attribution method and stop criteria defined before investing.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor AI Committee; in addition, the board in Transform

Evidence: P08 · P09 · P07 · P20 (adoption target) · P29 (board approval). Tool: T11.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G2.01 The hypothesis is falsifiable: it states what changes, in which metric, by how much, within what time frame and which result would refute it. P08 · T11 Yes Yes Yes Transform: allows greater uncertainty if G2.11 is met.
G2.02 The main and secondary metrics have a definition, formula, data source and measurement owner. P08 Yes Simpl. Yes —
G2.03 The baseline is measured with real data (period, source and method); if it is estimated, this is justified and approved by the decision-maker. P09 Conditionable Yes Yes Optimise: cost, time or errors. Augment: performance and cost. Transform: starting position of the market or customer, where it exists.
G2.04 The target and the success threshold are explicit and quantified. P08 Yes Yes Yes —
G2.05 The attribution method is chosen and justified; in Enterprise, a control group or the reason why one is not possible. P08 Conditionable Yes Yes —
G2.06 The expected value is expressed in money with a formula (units × unit value), is incremental, separates efficiencies, return and recurring cost, and declares the allocation if another case shares the result. P08 · T11 Yes Yes Yes Optimise: expected savings with a formula. Augment: economic effect of performance and cost. Transform: staged return hypothesis.
G2.07 Released capacity is reported separately from savings, with the planned way of realising or reallocating it. P08 Conditionable Yes Yes —
G2.08 The stop criteria are defined before investing, with a threshold and an evaluation date or milestone. P08 Yes Yes Yes Transform: stop criteria per stage.
G2.09 The ambition level is confirmed with evidence, and any change with respect to G1 is explained. P07 · T05 Yes Yes Yes —
G2.10 There is an adoption target: expected users, use and frequency. P08 · P20 Conditionable Yes Yes Optimise: recommended.
G2.11 Transform: the hypothesis includes learning milestones, an investment limit per stage and stop criteria per stage. P08 Yes — Yes Transform only.
G2.12 Transform: the board or its board committee has expressly approved the bet and this is recorded in the register. P29 Yes — Yes Transform only.
G2.13 The estimated investment up to G5 and the preliminary additional net value per euro are calculated. P08 · T11 Conditionable Simpl. Yes Transform: per stage.

Specific rules. If the confirmed ambition becomes Transform, the intensity becomes Enterprise and G2.11 and G2.12 apply before deciding. If a use case approved as Transform is reclassified to a lower level, the board is informed.

6.4 Feasibility (G3)

Purpose. Decide whether the use case is technically, economically, regulatorily and organisationally feasible with an acceptable risk. It is the main stop gate of the lifecycle.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor with risk clearance AI Committee

Evidence: P10 · P11 · P12 · P13 · P14 (if there is a supplier) · P04 (review) · updated P08. Tools: T06 · T07 · T09 · T13.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G3.01 Technical feasibility is demonstrated with the company's real data (technical proof or analysis on a representative sample), not only with assumptions. P10 Yes Yes Yes Transform: feasibility of the first stage.
G3.02 The data are available, with assessed quality (completeness, representativeness, timeliness and known biases) and an identified owner. P10 Conditionable Simpl. Yes —
G3.03 The legal basis for processing personal data and data minimisation are confirmed by the data protection function. P11 Yes ◆ Yes Yes —
G3.04 Full costs are estimated by category: construction, recurring (licences, model consumption, compute, operation) and adoption. P10 · T13 Yes Simpl. Yes —
G3.05 The expected net value is consistent with the risk appetite and the return horizon set in C2, and the benefits realisation plan is in draft with its business owner of the benefit. P10 · P08 · P62 Yes Yes Yes Optimise: positive expected annual net value within the horizon. Augment: in addition, feasibility of adoption and of the role change. Transform: feasibility of the first stage, stop criteria per stage and documented option value.
G3.06 The stop criteria approved at G2 remain in force and have not been relaxed without the approval of the body that authorised the use case. P08 · P29 Yes Yes Yes —
G3.07 The regulatory classification has been carried out with qualified legal judgement, is dated and signed, and states the company's role (provider or deployer). P11 · T07 Yes ◆ Yes Yes —
G3.08 There is no prohibited practice. If there is one, the only possible outcome is Stop. P11 Yes ◆ Yes Yes —
G3.09 It has been determined which impact assessments are required (data protection, fundamental rights, sector-specific), and those required before processing have been carried out or started with completion expected before G4. P11 Yes ◆ Yes Yes —
G3.10 The applicable regulatory obligations are linked to phase, role and evidence. P11 Conditionable Simpl. Yes —
G3.11 The risks are identified in the applicable categories and assessed using the scale in document 33 (probability × impact, inherent and residual). P12 · T06 Yes Simpl. Yes —
G3.12 No Critical residual risk lacks the express approval of the board or its board committee within the risk appetite; High risks are accepted by the AI Committee and Medium risks by the sponsor with risk clearance. P12 · P29 Yes ◆ Yes Yes —
G3.13 Each High or Critical residual risk has a mitigation and contingency plan with a control, owner and time limit. P13 Yes Yes Yes —
G3.14 Medium risks have a decided response (avoid, mitigate, transfer or accept) and an owner. P13 Conditionable Simpl. Yes —
G3.15 The intensity has been reviewed with the information from phase 3. P04 · T04 Yes Yes Yes —
G3.16 The impact on people has been assessed: affected roles and tasks, required capabilities and, where appropriate, information to or consultation with workers' representatives. P10 · P20 Conditionable Simpl. Yes Optimise: impact on tasks. Augment: feasibility of the role change. Transform: impact on the operating model.
G3.17 [GEN] The RT-GEN and RT-SEG typical risks are assessed: direct and indirect prompt injection, information leakage, erroneous or fabricated content, excessive permissions and unauthorised actions. P12 Yes ◆ Yes Yes —
G3.18 [GEN] The target autonomy level (A0–A3) is proposed and justified; if it is A2 or A3 with an effect on third parties, money, personal data or production systems, the intensity is Enterprise. P04 · P12 Yes ◆ Yes Yes —
G3.19 [GEN] The evaluation approach is defined: representative test sets, quality and security metrics and acceptance thresholds. P10 Conditionable Simpl. Yes —
G3.20 [TER] Each supplier is assessed at the requirement level that corresponds to it (N1–N3): security, processing and location of data, use of data for training, intellectual property, continuity, dependency and exit strategy. P14 · P55 · T09 Yes Simpl. Yes —
G3.21 [TER] The minimum contractual terms are set as a procurement requirement: confidentiality, prohibition on using the data for other purposes, incident notification, right to audit or equivalent reports (N2–N3) and return or deletion of data on termination. P14 · P56 Yes ◆ Yes Yes —
G3.22 [TER] The supplier provides, or undertakes to provide, the documentation that regulation requires of it and that the company needs to meet its own obligations. P14 · P11 Conditionable Rec. Yes —

Specific rules. Prohibited practices never get past this phase (01 §6.5). A Critical residual risk without the approval in G3.12 blocks G3. Pivot is admissible when the hypothesis does not hold but a reasonable alternative exists.

6.5 Design (G4)

Purpose. Approve a design that is controllable, supervisable and reversible, that covers the controls required by the risk classification, and in which each risk from phase 3 has a designed control.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor with risk clearance AI Committee

Evidence: P15 · P16 · P17 · P18 · P19 · P20 · P22 (test and pilot plan) · updated P11 and P14. Tools: T10 · T20.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G4.01 The architecture record describes components, integrations, environments, third-party dependencies and decisions with their alternatives. P15 Conditionable Simpl. Yes —
G4.02 The architecture guarantees traceability: automatic logging of inputs, outputs, versions and relevant decisions, with a defined retention period. P15 Yes ◆ Simpl. Yes —
G4.03 The lineage documents data sources and transformations, model versions, training or fine-tuning data and third-party foundation models. P16 Conditionable Simpl. Yes —
G4.04 The human oversight design sets out what the system decides, what a person validates and what is never delegated, and designates who intervenes, with what authority and with what means. P17 Yes ◆ Yes Yes —
G4.05 The transparency obligations are designed: notice of interaction with AI or of generated content where appropriate, and information and a route to human review in automated decisions about people. P17 Yes ◆ Yes Yes —
G4.06 Each Medium or higher risk from phase 3 has a designed control that is traceable to the risk register. P12 · P18 Yes Yes Yes —
G4.07 The security design covers identity and access, encryption, environment segregation, secrets management and AI-specific threats (data poisoning, model extraction, evasion). P18 Yes ◆ Simpl. Yes —
G4.08 Monitoring is defined (performance, degradation, bias, cost, security and use) with thresholds, alerts and an assigned operations owner. P15 · P03 Conditionable Simpl. Yes —
G4.09 There is a stop mechanism (deactivation or switch to manual mode) with an owner and a target activation time. P19 Yes ◆ Yes Yes —
G4.10 The rollback plan defines activation criteria, procedure, owner, operational alternative and treatment of data, and provides for its testing in phase 5. P19 Yes Simpl. Yes —
G4.11 There is an adoption plan with training, communication, support and measurement of use, and the benefits realisation plan is complete and signed by the business owner of the benefit. P20 · P62 · T20 Conditionable Simpl. Yes Optimise: how released capacity will be realised. Augment: role change and capacity reallocation. Transform: change in the operating model for the first stage.
G4.12 The test plan (functional, performance, bias, robustness and security) and the pilot design with the approved attribution method have acceptance criteria. P22 Conditionable Simpl. Yes Transform: the pilot measures the planned market or customer evidence.
G4.13 The required impact assessments are completed and their measures incorporated into the design. P11 Yes ◆ Yes Yes —
G4.14 If the system is high-risk, the obligations corresponding to the company's role (risk management, data governance, technical documentation, logs, instructions for use, human oversight, accuracy and robustness) are planned with an owner. P11 · P15 Yes ◆ — Yes —
G4.15 [AG] The agent has its own identity, distinct from that of any person, with managed, rotated and revocable credentials. P18 · T10 Yes ◆ Yes Yes —
G4.16 [AG] Permissions are minimal and the limits of action are explicit: permitted tools, operations, systems, amounts, recipients and volumes. P18 · T10 Yes ◆ Yes Yes —
G4.17 [AG] There is intent-based access control: each action is linked to the instruction and purpose that originate it and, if it is sensitive, is checked against the authorised purpose before being executed. P18 · T10 Yes ◆ Yes Yes —
G4.18 [AG] There is a kill switch that immediately stops the agent and revokes its credentials, with an owner and a planned test. P18 · P19 Yes ◆ Yes Yes —
G4.19 [AG] Sensitive or irreversible actions require prior human validation according to the approved autonomy level. P17 Yes ◆ Yes Yes —
G4.20 [GEN] There are defences against prompt injection and information leakage: separation between instructions and data, external content treated as untrusted, input and output filtering and restriction of tools. P18 · T10 Yes ◆ Yes Yes —
G4.21 [GEN] The evaluation set and its thresholds (quality, grounding of responses, harmful content and security) are approved before building. P22 Conditionable Simpl. Yes —
G4.22 [TER] The clauses required in G3.21 are incorporated into the contract or the draft under negotiation, and the integration with the supplier is documented. P14 · P56 · P15 Conditionable Yes Yes —

Specific rules. In Lite, G4 and G5 may be resolved in the same session if each criterion is assessed and recorded separately. High-risk classification implies Enterprise intensity, which is why G4.14 has no Lite column.

6.6 Go-live (G5)

Purpose. Authorise go-live when the solution works, delivers value under real conditions, the critical controls operate and operations are prepared.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor with risk clearance AI Committee after multi-level sign-off

Evidence: P21 · P22 · P19 (test) · updated P12 · P23 · P24 · P25 · P26 · P28 · P14 (contract). Tools: T03 · T08 · T10 · T11 · T12.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G5.01 The delivery report describes what has been built or integrated and the deviations from the design approved at G4, with their approval. P21 Conditionable Simpl. Yes —
G5.02 The functional and performance tests meet the acceptance criteria. P22 Yes Yes Yes —
G5.03 If the system affects people, the bias and non-discrimination tests have been carried out and the results are within the thresholds. P22 Yes ◆ Yes Yes —
G5.04 The robustness and security tests have been carried out and no critical or high vulnerabilities remain open. P22 Yes ◆ Simpl. Yes —
G5.05 [GEN] The evaluations on the approved set reach the thresholds, and direct and indirect prompt injection and information leakage tests have been passed. P22 · T10 Yes ◆ Yes Yes —
G5.06 [AG] The tests demonstrate that the limits of action and intent-based access control block unauthorised actions and that the kill switch stops the agent and revokes its credentials. P22 · P19 · T10 Yes ◆ Yes Yes —
G5.07 [AG] The autonomy level authorised for production is the one tested; any subsequent increase requires returning to G4 and G5. P18 · P23 Yes ◆ Yes Yes —
G5.08 The pilot has been run with the approved attribution method and its results reach the success threshold or do so with accepted conditions. P22 · T11 Conditionable Yes Yes Optimise: efficiency validated against the baseline. Augment: actual adoption and performance improvement measured. Transform: market or customer evidence (use, conversion, initial revenue or verified operational change).
G5.09 No stop criterion has been reached or, if one has been reached, the body that authorised the use case has expressly decided to proceed. P22 · P29 Yes Yes Yes —
G5.10 There is a plan to realise or reallocate the released capacity, with an owner and a date. P20 Conditionable Yes Yes Optimise: realise. Augment: reallocate. Transform: only if there is released capacity.
G5.11 The rollback plan has been tested and the actual rollback time meets the target. P19 Yes Yes Yes —
G5.12 The risk register is updated with the test results, and the acceptances of residual risk are recorded at the corresponding level (G3.12). P12 · T06 Yes ◆ Yes Yes —
G5.13 The critical security, compliance and human oversight controls are active and verified in the production environment, not only designed. P22 · P25 Yes ◆ Yes Yes —
G5.14 The people who exercise human oversight are designated, trained and have the authority and means to intervene. P17 · P20 Yes ◆ Yes Yes —
G5.15 The regulatory obligations prior to putting into service are met according to the company's role (for example, for high-risk: conformity assessment, registration and instructions for use where applicable; transparency in all applicable cases). P11 Yes ◆ Yes Yes —
G5.16 Monitoring and alerts are configured and tested. P25 Yes Simpl. Yes —
G5.17 The incident response plan defines severities S1–S4, escalation and applicable regulatory notifications (serious AI incident, data protection, DORA or NIS2) with their time limits. P26 · T08 Yes ◆ Simpl. Yes —
G5.18 The operations manual is available and accepted by the operations owner. P24 Conditionable Simpl. Yes —
G5.19 Users are trained and there is evidence of AI literacy among the staff who use or oversee the system. P20 Conditionable Yes Yes —
G5.20 [TER] The contract is signed with the required clauses and the supplier appears in the supplier register. P14 · P56 · P57 · T09 Yes ◆ Yes Yes —
G5.21 Value tracking is configured (frequency, source and validation owner) and the pilot results are recorded with their status (validated, declared or estimated). P28 · T12 Conditionable Simpl. Yes —
G5.22 The conditions from previous gates are closed or, if they do not affect critical controls, within their time limit. P29 · T03 Yes Yes Yes —
G5.23 Go-live is signed off: in Lite, with risk clearance; in Enterprise, with multi-level sign-off and no veto in force (section 9). P23 · T03 Yes ◆ Yes Yes —

Specific rules. A system in production without an approved G5 is a critical nonconformity (01 §12). The sign-offs in P23 refer to a specific version of the system: a significant change between sign-off and go-live requires signing off again.

6.7 Continuity review (R6)

Purpose. Periodically check that the system continues to work, deliver value and remain under control, and bring G7 forward if there are relevant deviations. Minimum frequency: quarterly in Enterprise and half-yearly in Lite.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor AI Committee

Evidence: P24 · P25 · P26 · P27 · P28 · P12 · P11 · P04 · P14 · P20. Tools: T08 · T10 · T12.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
R6.01 The review is carried out within its frequency. P29 · T01 Yes Yes Yes —
R6.02 The realised value is measured against the hypothesis, with validation status and proportion of validated value. P28 · T12 Yes Simpl. Yes Optimise: realised savings or reassigned capacity. Augment: sustained performance and adoption. Transform: progress against the stage milestones.
R6.03 Actual costs are compared with estimated costs and deviations are explained. P28 · T13 Conditionable Simpl. Yes —
R6.04 Performance is within thresholds and model changes or retraining are recorded. P25 · P27 Conditionable Yes Yes —
R6.05 If the system affects people, the monitored bias is within thresholds. P25 Yes ◆ Yes Yes —
R6.06 Incidents are recorded with severity, containment and closure, and notifiable incidents were notified on time. P27 · T08 Yes ◆ Yes Yes —
R6.07 Significant changes (purpose, model, data, autonomy, supplier or scope) have been assessed and, where appropriate, have gone through G4 and G5. P27 Yes Yes Yes —
R6.08 The regulatory classification, the impact assessments and the intensity remain valid in the light of changes in use or regulation. P11 · P04 Yes ◆ Yes Yes —
R6.09 The risk register is updated and new risks are assessed and accepted at the corresponding level. P12 · T06 Conditionable Simpl. Yes —
R6.10 There is evidence that the critical controls work: human oversight exercised, logs retained and stop mechanism available. P25 · P17 Yes ◆ Yes Yes —
R6.11 [AG] Permissions and credentials, intent logs and blocked or anomalous actions have been reviewed, and the kill switch has been tested in the period. P18 · P27 · T10 Yes ◆ Yes Yes —
R6.12 [TER] Supplier changes (model, terms, sub-processors), its incidents and compliance with the contract have been reviewed. P14 · P57 · T09 Conditionable Simpl. Yes —
R6.13 Post-market monitoring is carried out where regulation requires it. P25 · P11 Yes ◆ — Yes —
R6.14 Adoption is measured against the target. P20 · P28 Conditionable Yes Yes Optimise: recommended.
R6.15 Open conditions and nonconformities are within their time limit. P29 · T08 Yes Yes Yes —
R6.16 It has been assessed whether any deviation requiring G7 to be brought forward has occurred, and the conclusion is recorded in the register. P29 Yes Yes Yes —

Deviations that require G7 to be brought forward (criterion R6.16):

6.8 Scale or retire (G7)

Purpose. Decide with evidence whether the use case is scaled, iterated or retired.

Lite Enterprise
Verifies AI Office AI Auditor
Decides Sponsor AI Committee; in addition, the board to scale in Transform

Evidence: P28 · P30 · P07 · P12 · P27 · P24 · P14 · P29. Tools: T05 · T12 · T22.

Code Criterion Evidence Mandatory Lite Enterprise Optimise / Augment / Transform (if different)
G7.01 The realised value is consolidated with its validation status; to Scale, the value that justifies it is validated. P28 · T12 Yes Yes Yes Optimise: realised savings, not just released capacity. Augment: sustained performance and reassigned capacity. Transform: measured return and verified change in the operating model or the offering.
G7.02 There is an explicit conclusion on the hypothesis (confirmed, partially confirmed or refuted) against the threshold and the stop criteria. P30 Yes Yes Yes —
G7.03 The actual ambition has been reviewed with the classifier and any difference from the declared ambition is recorded in the register. P07 · T05 Yes Yes Yes —
G7.04 The accumulated risks, incidents and nonconformities for the period have been assessed. P12 · P27 Yes Simpl. Yes —
G7.05 The total actual costs, the actual annual net value and, if scaling is proposed, the additional net value per euro of the additional investment are recorded. P28 · P30 Conditionable Simpl. Yes —
G7.06 The lessons learned are recorded. P30 Conditionable Simpl. Yes —
G7.07 Scale: the extended scope, the additional investment and the new risks are described, and a new phase 0 will be opened. P30 Yes Yes Yes —
G7.08 Scale: operations have demonstrated stability (no open S1 or S2 incidents) and capacity for the new volume. P24 · P27 Conditionable Yes Yes —
G7.09 Scale in Transform: the board or its board committee has expressly approved it. P29 Yes — Yes Transform only.
G7.10 Iterate: the phase to return to, the reason and the time limit are defined. P30 Yes Yes Yes —
G7.11 Retire: the retirement plan records the date, coded reason, deciding body, replacement, treatment of data and models (retention and deletion), revocation of access and credentials, communication to those affected and update of the inventory. P30 · T22 Yes ◆ Yes Yes —
G7.12 [TER] Retire: termination with the supplier includes the return or certified deletion of data and the removal of access. P14 · P57 · P30 Yes ◆ Yes Yes —

Specific rules. The criteria for an outcome that is not proposed (for example, G7.07 to G7.09 when Retire is proposed) are recorded as Not applicable. Scale opens a new phase 0 for the extended scope; it does not by itself authorise the extension.


07Criteria differentiated by ambition level

7.1 Summary

This table develops 01 §7.6 and brings together the differences that the tables in section 6 set out criterion by criterion.

Gate Optimise Augment Transform
Opportunity (G1) Impact on people recommended (G1.10). Affected roles and teams identified (G1.10). Proposal communicated to the AI Committee (G1.06); senior management sponsor (G0.01).
Hypothesis (G2) Baseline for cost, time or errors (G2.03); expected savings with a formula (G2.06); adoption target recommended (G2.10). Baseline for performance and cost (G2.03); adoption target mandatory (G2.10). Learning milestones, investment limit and stop criteria per stage (G2.08, G2.11); board approval (G2.12).
Feasibility (G3) Positive expected annual net value within the C2 horizon (G3.05). Expected net value and feasibility of adoption and of the role change (G3.05, G3.16). Feasibility of the first stage, stop criteria per stage and documented option value (G3.01, G3.05); impact on the operating model (G3.16).
Design (G4) Plan for realising released capacity (G4.11). Plan for role change and reallocation (G4.11). Change in the operating model for the first stage; pilot that measures market or customer evidence (G4.11, G4.12).
Go-live (G5) Efficiency validated against the baseline; plan to realise released capacity (G5.08, G5.10). Actual adoption and performance improvement measured; reallocation plan (G5.08, G5.10). Market or customer evidence: use, conversion, initial revenue or verified operational change (G5.08).
Continuity review (R6) Realised savings or reassigned capacity (R6.02); adoption recommended (R6.14). Sustained performance and adoption (R6.02, R6.14). Progress against the stage milestones (R6.02).
Scale or retire (G7) Realised savings, not just released capacity (G7.01). Sustained performance and reassigned capacity (G7.01). Measured return and verified change in the operating model or the offering (G7.01); board approval to scale (G7.09).

7.2 Application rules

  1. The confirmed level applies. Ambition is proposed at G1, confirmed at G2 and reviewed at G7 (00 §5.2). Between G2 and G7 the criteria are assessed with the level confirmed at G2.
  2. Criteria are not mixed. An Optimise use case cannot justify G3 with option value; a Transform use case is not required to show positive net value within the C2 horizon at G3, but it is required to have an investment limit and stop criteria per stage.
  3. Reclassification has effects. Moving up to Transform requires Enterprise intensity and board approval before continuing. Moving down from Transform is reported to the board, and the criteria of the new level apply from that moment.
  4. Transform stages are controlled. Before committing the investment for a new stage, the AI Committee should record in P29 that the learning milestones of the previous stage have been reached and that no stop criterion has been triggered, informing the board.
  5. Released capacity is not savings. At no level is released capacity that has not been realised or reallocated accepted as realised value at G7 (measurement rule 3, 00 §6).

08Specific criteria for generative AI, agents and third parties

8.1 Map of criteria by topic

Topic G3 G4 G5 R6 G7
Generative AI evaluations G3.19 G4.21 G5.05 R6.04 —
Prompt injection and information leakage G3.17 G4.20 G5.05 R6.06 —
Autonomy level G3.18 G4.19 G5.07 R6.07 —
Agent identity and permissions G3.17 G4.15, G4.16 G5.06 R6.11 G7.11
Intent-based access control — G4.17 G5.06 R6.11 —
Kill switch — G4.18 G5.06 R6.11 G7.11
AI suppliers G3.20, G3.21, G3.22 G4.22 G5.20 R6.12 G7.12

The LV-AG checklist in document 22 brings together these criteria for agents and provides the content for tool T10.

8.2 Requirements by autonomy level

Requirement A0 · Assistance A1 · Recommendation A2 · Supervised action A3 · Autonomous action
Intensity According to 01 §9.2 According to 01 §9.2 Enterprise if there is an effect on third parties, money, personal data or production Enterprise if there is an effect on third parties, money, personal data or production
Own identity and minimal permissions (G4.15, G4.16) Not applicable If it accesses systems Mandatory Mandatory
Intent-based access control (G4.17) Not applicable Recommended Mandatory Mandatory
Prior human validation (G4.19) The person decides and executes For each action For sensitive or irreversible actions For actions outside the approved limits
Kill switch (G4.18, G5.06) General stop mechanism (G4.09) Recommended Mandatory and tested Mandatory, tested and checked at each R6
Oversight Review of the content by the person Record of the recommendation and of the human decision After-the-fact review by sampling Oversight of aggregates with alerts on the limits
Approval of the level At G4 At G4 At G4 and G5 Express at G4 and G5, with quantitative limits

Increasing the autonomy level of a system in production is a significant change: it requires returning to G4 and G5 (G5.07, R6.07).

8.3 Third-party AI by requirement level

The detail of levels N1–N3 is in document 36. For the purposes of the gates:

Level G3 G4–G5 R6
N1 · Standard Simplified P14; data use terms reviewed (G3.20, G3.21). Terms accepted and recorded (G5.20). Review of changes to the service (R6.12).
N2 · Enhanced Full P14; right to audit or equivalent reports and incident notification (G3.21). Clauses in a signed contract (G4.22, G5.20). Review of incidents and contractual compliance.
N3 · Critical In addition, exit strategy and DORA or NIS2 requirements where applicable (G3.20). In addition, continuity or exit test where appropriate. Review at each R6 with a dependency assessment.

09Multi-level go-live sign-off (G5)

9.1 Who signs off and what they check

In Enterprise, go-live requires multi-level sign-off with veto power (01 §6.7). Each sign-off is recorded in P23 and in T03 with the date, system version and criteria reviewed.

Signatory What they check as a minimum Reference criteria
Technical owner Solution delivered in accordance with the design, functional and performance tests, rollback tested, operational traceability. G5.01, G5.02, G5.11, G4.02
Risk and compliance Residual risk accepted at the corresponding level, prior regulatory obligations met, human oversight operational, stop criteria. G5.09, G5.12, G5.14, G5.15
Information security Security tests with no critical or high vulnerabilities, agent and injection controls, incident plan. G5.04, G5.05, G5.06, G5.07, G5.17
Data protection Legal basis, impact assessments, transparency and rights, contract with the supplier as regards data. G3.03, G4.05, G4.13, G5.20

The operations owner should also record their acceptance of operations (G5.18), which does not carry veto power. In Lite, risk clearance is sufficient (01 §9.3); if the system processes personal data, the risk owner should obtain the opinion of data protection before issuing it.

9.2 Sign-off and veto rules

  1. Three possible positions. Each signatory issues a favourable sign-off, a sign-off with reservations (only on Conditionable criteria, which become conditions) or a veto.
  2. The veto is reasoned. It indicates the codes of the criteria affected and what must be corrected.
  3. The veto blocks. With a veto in force, neither Proceed nor Proceed with conditions is possible. The AI Committee cannot lift a veto by majority; it can only decide to Iterate or Stop.
  4. Only the person who issued the veto can lift it, or their formal substitute in the second line, after checking the correction on a new version of the evidence.
  5. Disagreement. If the sponsor disagrees with the veto, they may escalate the matter to the board committee, which may request an independent opinion. A veto based on security, legal compliance or data protection cannot be replaced by a risk acceptance.
  6. Segregation. No signatory may have taken part in building the solution. If one person holds two sign-off functions, they sign off for each one and the auditor checks that there is no incompatibility.
  7. Validity. The sign-offs refer to a version of the system. A significant change, or the lapse of the maximum period set in C2 without putting the system into production, requires signing off again.
  8. Order. The AI Auditor verifies the evidence before the sign-offs; the committee decides after all of them.

10Audit criteria

10.1 Two points of control

Point Who Subject Outcome
Verification at the gate Verifier under 01 §7.5 (AI Auditor in Enterprise) Evidence and status of each criterion before the decision. Verification opinion (10.2) that accompanies the request.
Subsequent audit AI Auditor or third line, according to the audit plan (document 38) Sample of gates, decisions, conditions, operational records and retirements for a period. Report with an outcome per audited item and classified findings (10.5).

The AI Auditor may not have taken part in the design, construction or operation of the use case, nor report hierarchically to its sponsor (01 §8.1).

10.2 Outcomes

Outcome In the verification of a gate In a subsequent audit
Conformant Complete and valid evidence; criterion statuses correctly assigned. The request goes to the deciding body. Criteria correctly assessed, valid evidence and a decision consistent with the rules. No findings, except opportunities for improvement.
Conformant with observations Shortfalls that do not affect Yes criteria or the validity of the evidence. The request goes to the decision-maker with the observations, which may become conditions. Findings that do not invalidate the decision: observations and minor nonconformities.
Nonconformant Some mandatory evidence is missing or some evidence is not valid. The request goes back to the team without a decision. At least one major or critical nonconformity.

A Conformant opinion does not mean that the use case should proceed: it means that the body can decide on a verified basis.

10.3 What is sampled

The sizes are indicative; the company sets them in C2 or in its audit plan and recalibrates them in C5.

Subject Population Selection Indicative size
Lite gates Lite gates decided in the half-year. Random and targeted. At least 10% with a minimum of three, including at least one G5.
Enterprise gates Enterprise gates decided in the period (already verified by the auditor). Targeted and random. All G5s and at least 25% of the rest.
Criteria within a gate All the criteria for the gate. All Yes and Yes ◆; a sample of Conditionable and Recommended; all Not applicable on ◆ criteria. —
Evidence Evidence linked to the selected criteria. Rules EV.01–EV.14 on all evidence for Yes ◆ criteria; EV.05 and EV.09 on all evidence. —
Conditions Conditions open and closed in the period. All expired conditions and a sample of the closed ones. At least 25% of the closed ones.
Operational records Incidents, changes, human interventions and agent actions of systems in production. Targeted at S1, S2 and significant changes; random for the rest. According to the audit plan.
Stops and retirements Use cases stopped or retired in the period. Random. At least one per quarter, if any.

Targeted selection. Priority is given to: use cases with two or more iterations at a gate; expired conditions; reference time limits exceeded; changes of intensity from Enterprise to Lite; Not applicable on ◆ criteria; decisions taken on the same day as the request; High residual risks; Transform use cases; A2 or A3 agents; N3 suppliers; systems with incidents in the period.

10.4 Audit tests

Test What the auditor does Example
Inspection Examines the evidence against the criterion and the EV rules. Checks that the baseline in P09 has a period, source and method.
Time traceability Compares the dates of the evidence with the events in T01. Detects a pilot report dated after the G5 decision.
Re-performance Repeats a calculation or a check. Recalculates the net value in P28; compares an agent's actual permissions with those approved in P18.
Observation Witnesses the performance of a control. Attends the kill switch or rollback test.
Interview Checks what is documented with the people involved. Asks the person who exercises human oversight how they intervene and when they have done so.
Consistency Compares pieces of evidence with each other. Risks in P12 against controls in P18; value in P08 against P10 and P28.

10.5 Classification of findings

Findings are classified using the nonconformity scale in 01 §12, preceded by the observation, which is not a breach.

Nonconformity management
A single process for all deviations. Only the AI Auditor can close a nonconformity
1Detection 2Classifi-cation 3Containment 4Root causeanalysis 5Correctiveaction 6Re-audit Effective Closure by AI Auditor Not effective: return to root cause analysis
Source: SEVEN-G
Type Definition Examples in gates and audits
Observation Opportunity for improvement without a breach of a requirement. Recommended criterion omitted without justification; evidence that is correct but difficult to locate.
Minor nonconformity Breach with no impact on the decision. Incomplete evidence on a Conditionable criterion that does not change the outcome; delay in updating T01; Not applicable with insufficient justification on a non-◆ criterion.
Major nonconformity Breach that invalidates the decision or affects a relevant control. Evidence prepared after the fact; self-approval or omitted verification; Proceed recorded with a blocking criterion; stop criteria relaxed without approval; expired condition on a relevant control; R6 omitted; Transform without board approval at G2; unjustified Not applicable on a Yes criterion; third iteration without escalation.
Critical nonconformity Breach with an immediate risk to people, legal compliance or the company. System in production without an approved G5; prohibited practice; serious incident not notified; critical control deactivated or non-existent in production (human oversight, logs, kill switch); agent operating above its approved autonomy level; go-live with a veto in force; Critical residual risk in production without board approval.

Classification rules

  1. Classification is based on the most serious effect on the decision, people or compliance.
  2. A breach of a Yes ◆ criterion in a system in production is, at a minimum, a major nonconformity.
  3. Any finding that invalidates a gate decision is, at a minimum, a major nonconformity.
  4. A minor nonconformity that recurs three times in twelve months in the same use case or process is raised to major (37 §3.3).
  5. The deliberate concealment or alteration of evidence is, at a minimum, a major nonconformity and is reported to the board committee.

10.6 Effects on the decision and time limits

Type Effect on the gate Containment Action plan Reported to
Critical The gate is invalidated. Immediate (maximum 48 hours), including stopping the system if necessary. Maximum 10 days. AI Committee and board committee.
Major If it invalidates the decision, the use case returns to Awaiting gate and is verified again. If it is already in production, the committee decides whether to maintain operation with containment measures. Maximum 10 days. Maximum 30 days. AI Committee.
Minor The decision stands. Not required. Before the next gate or review. AI Office.

The time limits are reference values and the company may adjust them in C2 without exceeding those established by applicable regulation (01 §12). Each nonconformity is recorded with code NC-AAAA-NNN in T08 and managed through the process in document 37.

10.7 Minimum content of the audit report

Scope and period · population and sample with selection criterion · tests performed · outcome per audited item (Conformant, Conformant with observations or Nonconformant) · findings with the code of the affected criterion or EV rule, classification, cause and owner · open nonconformities in T08 · follow-up of previous findings · conclusion on the functioning of the gates in the period.

The report is drafted with P60.


11Gate decision record (P29)

Every gate decision and every continuity review is documented in P29 and reflected in T03. The record must contain, as a minimum:

Block Fields Mandatory
Identification Use case code (IA-AAAA-NNN); gate; iteration number; intensity; ambition level; technology; autonomy level; suppliers. Yes
Dates Request, verification and decision; deadline according to the reference time limit. Yes
Evidence submitted For each piece of evidence: P code, version, author, date, link and result of the EV rules. Yes
Status of the criteria For each criterion: code, status (Met, Not met, Not applicable or Pending), R and D dimensions, linked evidence, comment and justification for Not applicable. Yes
Summary Applicable criteria, degree of compliance, blocking criteria and open conditionable criteria. Yes
Verification Verifier, opinion (Conformant, Conformant with observations or Nonconformant), observations and declaration of absence of conflict. Yes
Sign-offs (G5) In Enterprise: each signatory, position (favourable, with reservations or veto), reason and date. In Lite: risk clearance. Yes at G5
Decision Outcome; reason; coded reason from the taxonomy if Stop or Retire; body and people deciding; abstentions; dissenting positions. Yes
Conditions For each condition: identifier, description, linked criterion, owner, time limit, means of verification and consequence on expiry (Iterate). If there are conditions
Higher approvals Approval by the board or the board committee (Transform at G2 and G7; Critical residual risk) with a reference to the minutes or to the register of recommendations and decisions. Where applicable
Pivot Hypothesis discarded, alternative chosen and alternatives considered. If pivoting
Next step Next phase or phase returned to; planned date of the next gate or R6. Yes
Lessons Lessons learned in stops and retirements. If Stop or Retire

No weighted scoring is used: criteria are either met or not, with evidence, and no average compensates for a blocking criterion.


12Associated tools and templates

Name Use in this document
Gate manager (T03) Criteria with code and applicability; statuses, R and D dimensions, verification, sign-offs, decision and conditions; calculation of the degree of compliance and blocking of Proceed when there are blocking criteria.
Other tools in document 03 (T01, T02, T04–T13, T20, T22) Time traceability and evidence for the criteria, according to the Evidence column.
Go-live sign-off (P23) Multi-level sign-off and veto (section 9).
Gate decision record (P29) Format in section 11.
Block H templates (P01–P31) Evidence for each criterion.

Document Relationship
01 · Foundational methodology Normative reference: phases, gates, decision rules, roles, intensity and nonconformities.
03 · Tools and use case register Criterion statuses, funnel metrics and tool T03.
20 · Phase manuals Activities that produce the evidence assessed here.
22 · Gate checklists Binary controls with the same codes, and the LV-EV and LV-AG checklists.
30 · Governance model Higher bodies, substitutions and escalation after two iterations.
33 · AI risk methodology Scales, acceptance levels and typical risks.
34 · Regulatory mapping Obligations linked to G3.10, G4.14 and G5.15.
35 · AI and agent security Autonomy levels and agent controls.
36 · AI third parties and suppliers Requirement levels N1–N3.
37 · Nonconformities and incidents Process for managing findings and severities.
38 · AI audit framework Audit plan, auditor competence and sampling.
40 · Value measurement rules Amount statuses, formulas and attribution.

14Version control

Version Date Changes
0.1 16-09-2026 First version. Merges the two versions of the gate and audit criteria in the previous material with the current model in 01: 128 criteria coded by gate, intensity and ambition, with criteria for generative AI, agents and third parties; valid evidence, degree of compliance, multi-level sign-off with veto, audit and decision record. Consistency adjustments with 01 (segregation of duties in Lite, R6 outcomes, agent criterion) and with 34 and 37.
0.2 01-10-2026 New section 4.3, reference rather than reproduce: evidence the company already has meets the criterion if it covers what is required, with requirements of reference, owner, coverage and validity, and a table of usual equivalences; EV.10 accepts referenced evidence.
0.3 01-10-2026 New section 2.5, criteria at Express intensity (all applicable "Yes ◆" criteria and those that sustain the core; R6 and G7 as Lite); 3.4 includes Express and G3 in writing.