Template P10 · Feasibility assessment

Feasibility assessment

Brings together the technical, data, economic, organisational, regulatory and risk evidence needed to decide at G3 whether the use case proceeds or stops.

Fernando García VarelaVersion 0.1 (working draft)16-09-2026Draft for review

01Instructions for use

Aspect Guidance
When it is used In phase 3 (Feasibility and risk), before G3, which is the main stop gate in the lifecycle.
Who completes it The AI Product Owner (economic and organisational feasibility) and the AI Technical Owner (technical and data feasibility). The risk owner provides the summary of P11, P12, P13 and P14.
Who verifies it Lite: AI Risk Owner. Enterprise: AI Auditor. If the risk owner has prepared parts of this document, in Lite the AI Office or the AI Auditor verifies it.
Who decides Lite: sponsor with risk clearance. Enterprise: AI Committee.
Gate at which it is reviewed Feasibility. (G3)
Tool It has no tool of its own; costs can be calculated with T13 and value with T11.
Lite versus Enterprise Lite may omit the fields and blocks marked (Enterprise).

Completion rules:


02Identification

Field Content Guidance
Use case code IA-AAAA-NNN.
Use case name
Confirmed ambition level Optimise · Augment · Transform.
Intensity Lite · Enterprise (reviewed at G3 with P04).
Document version
Date DD-MM-AAAA.
Authors Names and roles by block.

03Summary and recommendation

Field Content Guidance
Technical conclusion Feasible · Feasible with conditions · Not feasible.
Data conclusion Feasible · Feasible with conditions · Not feasible.
Economic conclusion Feasible · Feasible with conditions · Not feasible.
Organisational conclusion Feasible · Feasible with conditions · Not feasible.
Regulatory and risk conclusion Feasible · Feasible with conditions · Not feasible.
Recommendation to the decision-making body Proceed · Proceed with conditions · Iterate · Pivot · Stop.
Main reason Two or three sentences.

04Technical feasibility

Field Content Guidance
Technical approach assessed Type of solution, models, build or buy.
Tests carried out Proof of concept or experiment, with dates and real data used.
Integration Systems with which it must be integrated and complexity identified.
Scalability and performance Expected volumes and test results.
Maturity of the technology and the supplier Stability, support, roadmap.
Internal capabilities Available knowledge and gaps.
Preliminary reversibility How it could be stopped or reverted to the previous process.
Requirement Required threshold Result obtained Met
Yes · No · Partial
(illustrative example) Correct answers on order status (reviewed sample) ≥ 95% 96.8% over 1,000 test conversations Yes
(illustrative example) Response time ≤ 5 s in 95% 3.2 s Yes
(illustrative example) Resistance to prompt injection 0 leaks of other customers' data 2 leaks in 300 test attacks No

05Data feasibility

Source Availability Quality Legal basis and purpose Biases or limitations Action required Result
Available · Partial · Not available Completeness, accuracy, timeliness Feasible · With conditions · Not feasible
(illustrative example) Order logistics system Available via API 99% of orders with status updated in less than 1 h Performance of the contract with the customer Does not reflect issues with external carriers Integrate carrier notifications With conditions

06Economic feasibility

6.1 Full costs

Category One-off investment (€) Annual recurring cost (€) Assumptions
Licences
Model consumption
Compute and infrastructure
Data
Build staff
Operations staff
Suppliers and services
Control and compliance
Adoption and training
Total

6.2 Economic result

Item Value Guidance
Expected annual efficiencies (€) From P08, updated with what has been learned in phase 3.
Expected annual return (€) From P08.
Annual recurring cost (€) From 6.1.
Expected annual net value (€) Efficiencies + return − recurring cost.
Additional investment required (€) From 6.1.
Additional net value per euro Expected additional annual net value ÷ additional investment required.
Horizon set in C2 Is the expected net value consistent with the horizon? Yes · No.
Scenarios (Enterprise) Annual net value in prudent, central and favourable scenarios, with the assumptions that change.
Status of the amounts In this phase, normally estimated.

07Organisational and adoption feasibility

Field Content Guidance
Users and change in their work Which tasks change, how many people and to what extent.
Effect on roles and jobs Role changes, capacity reassignment, training needs.
Readiness for adoption Evidence: user tests, resistance detected.
Capacity to operate Who will operate the system and whether they have the capacity.
Labour relations (Enterprise) Information or consultation obligations and status.
Preliminary adoption plan Reference to P20, which is completed in phase 4.

08Regulatory and risk feasibility

Field Content Guidance
Regulatory classification Taxonomy in 03 §3.3, with reference to P11 and to the legal validation.
Prohibited practice Yes · No. If "Yes", the recommendation is Stop.
Impact assessments Data protection impact assessment and fundamental rights impact assessment: carried out, not required or pending.
High and Critical residual risks Number and reference to P12; acceptance approval where applicable.
Mitigation and contingency plan Reference to P13.
Suppliers Requirement level and conclusion of P14.
Fit with the C2 risk appetite Yes · No, with justification.

09Check by ambition level at G3

Reference: 01 §7.6.

Level What must be demonstrated Result Met
Optimise Positive expected annual net value within the horizon set in C2. Yes · No · Not applicable
Augment Feasibility of adoption and of the role change, in addition to the expected net value.
Transform Feasibility of the first stage; stop criteria per stage; documented option value.

10Proposed conditions

No. Condition Deadline Owner Gate at which it is verified
1
(illustrative example) 1 Fix the prompt injection vulnerability and repeat the test with 0 leaks. Before G4 Technical owner G4

"Proceed with conditions" is not permitted for critical security, legal compliance or human oversight controls (01 §7.3). In the example, the condition affects a critical security control: the correct recommendation would be Iterate until it is fixed.


11Quality criteria

The formal G3 criteria are in document 21 (see criteria G3.xx).

# Check Status
1 Technical feasibility is based on tests with real data. Met · Not met · Not applicable · Pending
2 Each data source has its availability, quality and legal basis assessed.
3 Costs cover the nine categories and distinguish investment from recurring cost.
4 Annual net value and additional net value per euro are calculated with status.
5 The impact on people is assessed.
6 P11, P12, P13 and, if there are suppliers, P14 exist.
7 There are no prohibited practices or Critical risks without the required approval.
8 The G3 criteria for the ambition level are applied.
9 The proposed conditions do not affect critical controls.

12Approval and verification

Function Role in SEVEN-G Name and position Date Signature or reference
Prepares (economic and organisational) AI Product Owner
Prepares (technical and data) AI Technical Owner
Issues risk clearance AI Risk Owner
Verifies Risk owner (Lite) · AI Auditor (Enterprise)
Decides Sponsor with risk clearance (Lite) · AI Committee (Enterprise)

Segregation of duties: nobody verifies a block they have prepared. Risk clearance and verification are separate acts and must be recorded separately.


13Version control

Completed document

Version Date Author Changes

Template

Version Date Changes
0.1 16-09-2026 First version. Structure aligned with 01 §6.5 and §7.6 and with the cost categories in the common specification §5.7.