SEVEN-G
Document 90 · 01-10-2026

Document 90 · Implementation guide

SEVEN-G implementation guide

How to adopt the framework: scope, prerequisites, 90-day plan and roadmap up to being able to declare that it is applied

Fernando García VarelaVersion 0.3 (working draft)01-10-2026Draft for review
2implementation scopes
13weeks of initial plan
7conditions for declaring that it is applied
18months as the maximum roadmap horizon

01Purpose and scope

This guide explains how an organisation adopts SEVEN-G for the first time. It develops the first implementation envisaged in 01 §5.3 —concentrating C1 to C3 into ninety days— and the subsequent roadmap until the conditions for the declaration of application are met (01 §14).

It is aimed at whoever leads the implementation (normally the head of the future AI Office), the sponsor in senior management and the risk, compliance and internal audit functions.

Where to start according to the starting point. Not every company starts in the same way: one with no AI, another with predictive models in production and another with many pilots need a different order. Document 96 classifies the starting point (six archetypes and five modifiers) and orders the milestones of this guide for each case, without changing what is required in the end; tool T23 runs the questionnaire and produces the plan.

This document does not constitute legal advice.

1.1 What implementing SEVEN-G means

Milestone What has been achieved
Day 90 Diagnosis with evidence (C1), direction proposed or approved (C2), first portfolio (C3), bodies, roles, gates, metrics and reporting cadence up and running.
Months 4–18 The framework operates on a steady-state basis: new use cases go through the lifecycle, existing ones are regularised, the board exercises oversight with the dashboard.
Declaration of application The fourteen core rules (01 §14.1) are met, substantiated with the (§14) questions of document 11 in a verified assessment and with the audit in 38 §11.

02Choosing the implementation scope

2.1 Company-level Lite or Enterprise

The implementation scope is a company decision on how it organises its governance. It does not replace the intensity of each use case: in a company with a Lite scope, any use case that meets a criterion in 01 §9.2 is managed with Enterprise intensity.

Aspect Lite scope Enterprise scope
Typical organisations Medium-sized, unregulated or with light sector-specific regulation, small portfolio. Regulated groups (financial services, insurance, energy, healthcare, public sector), several subsidiaries or countries, broad portfolio.
AI Committee Existing management committee with an extended mandate. Specific committee or existing committee with its own session and the composition in 01 §8.3.
Board committee Whichever committee already oversees risk or audit, with AI as a recurring item. Risk, audit or technology committee with an express mandate over AI.
AI Office One person with part-time dedication and occasional support. Methodology, portfolio and measurement team.
AI Auditor Internal audit or external auditor, by sampling in Lite and at every Enterprise gate. Third line with assigned AI Auditors.
Maturity Verified assessment. Verified assessment and, at least every two years, an independent one (document 11).
Board dashboard Aggregated. By use case for Enterprise ones.
Indicative horizon up to 01 §14 6 to 12 months. 12 to 18 months.

Size does not determine the scope: the criteria in section 2.2 do. A medium-sized company without sector-specific supervision or high-risk systems applies a Lite scope; a small company subject to prudential supervision applies an Enterprise scope. Both scopes apply the same lifecycle, the same evidence and the same segregation of duties rules; what changes is how the bodies and verification are organised.

2.2 Selection criteria

An Enterprise scope is chosen if at least one of these criteria is met; otherwise, Lite:

  1. The company is subject to prudential or sector-specific supervision that requires formal governance of technology or model risk (for example, financial institutions subject to DORA).
  2. It has or plans high-risk AI systems under the EU AI Act.
  3. It has or plans agents with A2 or A3 autonomy over customers, money, personal data or production systems.
  4. It operates as a group with several companies or countries that must follow a common framework.
  5. The approved or planned portfolio includes several simultaneous Transform bets (indicatively, three or more; value to be calibrated in C2).

A single Transform bet does not change the scope. That use case is managed with Enterprise intensity (01 §9.2) and the board approves it at G2 and, if it scales, at G7 (01 §7.5); the rest of the portfolio remains in a Lite scope. The scope is reviewed at each annual review (C5), or earlier if the company comes to meet any of these criteria.

2.3 Perimeter

The perimeter may be the whole company or a part of it (a subsidiary, a country, a business unit). Implementing first in a reduced perimeter is valid, but the declaration of application only covers the implemented perimeter and must say so. The AI system inventory, however, should cover the whole company from the outset, because risk does not respect perimeters.

2.4 Minimum path in a Lite scope

Why it matters. A medium-sized company does not need to go through the whole library to get started. It needs to know what is mandatory from day one, what is added only when an Enterprise use case appears and what it can consult when needed. Without that path, the framework looks heavier than it is and the company ends up applying Enterprise to everything or applying nothing.

Mandatory from the start

Element Minimum in a Lite scope Reference
Initial reading Documents 00 and 01, this guide, the adaptation to small organisations in the governance model and, in the gate criteria, the Lite column of each gate. 00; 01; 30 §11; 21 §2.1
Three safeguards Those who build do not verify or decide on their own work; the risk clearance is issued by someone independent of the team; the board approves the direction and the risk appetite. 30 §11
Bodies Board with an AI item at least quarterly; executive committee with a monthly AI item; AI Office of one part-time person. 01 §5.2; 30 §11; section 7
Inventory All AI systems —in-house, third-party, corporate use and unauthorised use— with a completeness statement. It is not reduced in Lite. 32; P05; T01
Intensity Determination for each use case: in phase 0, at G3 and at each R6. 01 §9; P04; T04
Express use cases Small, internal and reversible ones that meet the eligibility in 01 §9.4 go through the same gates with the reduced list of criteria and a living record; the Express threshold is approved in C2. 01 §9.4; 21 §2.5; P01 §14; P04 §5.1
Evidence for a Lite use case The evidence that the gate criteria mark "Yes" or "Simpl." in the Lite column, with templates without the (Enterprise) fields. No mandatory evidence is omitted: it is simplified. 01 §6.10; 21 §2.1; P01–P31
Gates G0–G2 in one session, G3 separately, G4–G5 in one session, half-yearly R6 and G7. Each gate keeps its criteria and its record in P29. 21 §3.4
Verification and decision The AI Office verifies; the sponsor decides, with risk clearance at G3, G4 and G5; the AI Auditor reviews a sample of Lite gates every half-year. 01 §9.3; 21 §10.3
Risks Risk register from phase 3 with the scale in document 33. 33; P12; T06
Value Measurement rules, baseline and tracking of realised value; aggregated board dashboard. 40; P09; P28; T17
Diagnosis Maturity with a verified assessment and transformation index at C1 and at each C5. 11; 12; T15; T14

Added only when a use case meets an Enterprise criterion

What is added Reference
Separate gates, full templates and decision by the AI Committee (by the board for Transform). 01 §7.5, §9.3
AI Auditor at every gate of that use case, external if there is nobody independent in-house. 01 §9.3; 38
Multi-level sign-off with veto for go-live and quarterly R6. 21 §9; P23
Visibility by use case in the board dashboard. 60; T17
Depending on the criterion met: regulatory classification and impact assessments; security of A2 or A3 agents; N2 or N3 requirements for suppliers. 32, 34, P11; 35, P18; 36, P14

The rest of the library is consulted when needed: ambition and portfolio (10, 13, 14), phase manuals and checklists (20, 22), adoption and people (23, 50), policies (31), incidents (37), indicators and costs (41, 42, 43), data, operation and construction (51, 52, 53), board (60, 61, 62) and application cases (92), which includes Lite use cases of medium-sized companies.

The matrix in document 94 extends this path to the whole library: it gives the obligation level of each document, template and tool, the triggers that activate each module and what can be grouped at the gates; each document summarises its minimum part in its "The essentials" box. The SEVEN-G course follows the same path in short modules.


03Prerequisites

Prerequisite Compliance criterion
Senior management sponsorship Implementation mandate signed by the executive chair or the chief executive officer, with objective, perimeter, scope and time limit.
Board awareness The board or its board committee is aware of the plan and has a session reserved in weeks 12–13 to approve C2.
Implementation lead Appointed person with sufficient dedication (indicatively, most of their working time during the 90 days in Enterprise).
Core team Representatives from business, technology, data, risk, compliance, security, data protection, human resources and management control, with allocated time.
Third line informed Internal audit is aware of the plan and designates who will verify maturity.
Legal counsel Available for the regulatory classification of priority systems.
Access to information Procurement, licences, supplier contracts, architecture, risk register and budgets.
Register support T01 with its inventory (T02) or, if the company prefers, a spreadsheet with the fields of the data model in 03 §4 (and the record in 03 §3.3).
No general moratorium AI activity continues during implementation; only what the diagnosis identifies as unacceptable risk is stopped.

0490-day plan

4.1 Overview

90-day plan
Three months, three outcomes and one board decision
flowchart LR
  S0["Week 1: mandate and kick-off"] --> M1["Month 1: C1 diagnosis"]
  M1 --> H1{"Milestone 1: C1 report accepted"}
  H1 --> M2["Month 2: risks, opportunities and C2 draft"]
  M2 --> H2{"Milestone 2: map approved and C2 ready"}
  H2 --> M3["Month 3: governance structure and C3 portfolio"]
  M3 --> H3{"Milestone 3: board and committee approval"}
  H3 --> R["Week 13: steady state"]
  classDef ok fill:#d9ebe0,stroke:#0d7680,color:#1a1817
  classDef med fill:#f2dfce,stroke:#0f5499,color:#1a1817
  class H1,H2,H3 med
  class R ok
Source: SEVEN-G

Each milestone is accepted by the implementation sponsor together with the AI Committee (or the management committee while the former has not been set up). If a milestone is not met, it is replanned for the following month; no progress is made with empty deliverables.

4.2 Month 1 · Diagnosis (C1)

Week Activities and deliverables Owner Documents, templates and tools Completion criterion
1 · Kick-off Implementation mandate (P32); Lite or Enterprise scope and perimeter; core team; calendar of bodies with the board session reserved; internal communication; request for maturity evidence; cut-off date. Sponsor and implementation lead 00, 01, 90; evidence list in document 11 Mandate signed; board session reserved; evidence request sent.
2 · Inventory Census of AI systems: in-house, third-party, corporate use and unauthorised use (based on procurement, licences, contracts and security controls). Registration with actual status. Initial screening of Enterprise criteria and possible prohibited practices. AI Office with technology, procurement and security 03; P05; T02, T01; T04 Each area head signs an inventory completeness statement (P32, annex). Possible prohibited practices escalated immediately.
3 · Evidence and interviews Maturity interviews by dimension; review of evidence and sampling; collection of current value and cost with their status; data for the eight index signals. Assessment team 11; 12; 40; T15, T14, T12 Seven dimensions with at least two interviews each; samples selected.
4 · C1 report Scoring, calibration and independent verification of maturity; transformation index profile; current sphere map; portfolio value and cost; C1 report (P33, with maturity from P34). Lead assessor; independent verifier 10, 11, 12; T15, T14, T16 Milestone 1: C1 report verified and accepted. Urgent risks treated as a nonconformity (01 §12).

4.3 Month 2 · Risks and opportunities

Week Activities and deliverables Owner Documents, templates and tools Completion criterion
5 · Risks Workshops by sphere on existing systems; main risk matrix using the scale in document 33; regulatory classification of priority systems; regularisation order. AI Risk Owner with legal counsel 33, 34, 32; P11, P12; T06, T07 Systems with Enterprise criteria classified or with a classification date; High and Critical risks with an owner.
6 · Opportunities Workshops by sphere with the reference questions; opportunity portfolio with an understandable record; proposed ambition; value with a formula marked as estimated. AI Office with the business areas 10, 61; P06, P07, P31; T05 Opportunities from all spheres with value at the planned ambition, or a record that there are none.
7 · Consolidation and C2 draft Risks and opportunities by sphere with owner, economic impact and timeframe; draft AI thesis, ambition per sphere and risk appetite; draft thresholds (Enterprise investment, horizon, reference time limits, nonconformity time limits, concentration limits, maturity weights). Implementation lead with senior management 13, 14; T19 Complete draft with all the sections of C2 (01 §5.1).
8 · Challenge Review with senior management and with the second line; proposed framework budget and envelopes by ambition lane; regularisation time limits. Sponsor 13, 14 Milestone 2: risk and opportunity map approved; C2 proposal ready for the board.

4.4 Month 3 · Governance structure (C2 and C3)

Week Activities and deliverables Owner Documents, templates and tools Completion criterion
9 · Bodies and roles Mandates of the AI Committee, the AI Office and the board committee (P38); roles in 01 §8 in existing use cases with an incompatibility check; AI Auditor designated. Sponsor; board secretariat 01 §8, 30; P03; T01 Mandates drafted; roles assigned without incompatibilities.
10 · Gates and policies Gate criteria (21) and checklists (22) adopted; equivalences between the evidence the company already produces and the templates it covers (21 §4.3), so that it is referenced rather than copied; reference time limits; corporate and acceptable use policy; nonconformity process. AI Office; compliance 21, 22, 31, 37; P04, P29; T03, T08 Gate manager configured; policies in final draft.
11 · Metrics, reporting and portfolio Measurement rules adopted; first version of the board dashboard; register of recommendations; reporting calendar (01 §5.2); first prioritised portfolio with envelopes, tranches and regularisation plan. AI Office; management control; committee 40, 60, 62, 14; P28; T17, T18, T01, T16 Dashboard generated with inventory data; portfolio with scoring and owners.
12 · Approvals The board approves the thesis, ambition per sphere, risk appetite, thresholds and corporate policy (C2). The committee approves the portfolio, gates, metrics and regularisation plan (C3). Sponsor; AI Committee; board 13, 14, 31 Minutes with the approvals.
13 · Steady state First ordinary meeting of the committee; first gates under the new model; 6–18-month roadmap approved; lessons from the implementation; communication to the organisation. Implementation lead 90; T01, T03 Milestone 3: criteria in section 4.5 met.

If the board cannot approve C2 in week 12, the portfolio operates with provisional criteria approved by the committee, no Transform use cases are approved and approval is taken to the next board session.

4.5 Completion criteria for the 90 days

# Criterion Evidence
1 Inventory with a completeness statement from all areas in the perimeter. T02; signed statements (P32, annex).
2 Maturity assessment verified and transformation index calculated. C1 report (P33); T15; T14.
3 Risks and opportunities by sphere with owner, economic impact and timeframe. Approved map.
4 Thesis, ambition per sphere, risk appetite and thresholds approved by the board, or approval date set with provisional criteria. Minutes.
5 Bodies with a mandate, roles assigned without incompatibilities and AI Auditor designated. Mandates; P03.
6 Gates, reference time limits and nonconformity process operational. T03; T08.
7 Board dashboard and register of recommendations with real data. T17; T18.
8 First prioritised portfolio and regularisation plan with time limits. Committee minutes; T01.
9 Every new use case goes through G0 before consuming budget from week 13. T01.

05Regularisation of existing use cases and systems

The full procedure is in document 14, section 11. In the implementation journey it is milestone HI-12, whose priority depends on the starting point (document 96). During implementation it is applied as follows:

Type When Treatment
Systems in production with Enterprise criteria Classification in month 2; review equivalent to G7 within six months of C2. First those that are high-risk, involve decisions about people, direct exposure and agents that act.
Other systems in production Within 12 months of C2. Review equivalent to G7 with simplified evidence.
Use cases under construction or in pilot From week 13. They are placed in the phase that corresponds to their actual evidence and pass the next gate.
Corporate use of general-purpose AI Inventory in month 1; acceptable use policy in month 3. Authorise, replace or block; training and technical controls.
Unauthorised use detected From month 1. Nonconformity with containment proportionate to the risk; authorise, replace or block (01 §1.2).

Regularisation documentation is identified as such and bears its actual date. It does not substantiate past gates.


066- to 18-month roadmap

6.1 Stages

Period Objective Outcomes
Months 4–6 · Consolidation Ensure the lifecycle works with all new use cases. Complete register; first verified gates; regularisation of priority systems; first quarterly board review with the dashboard; training in SEVEN-G roles; AI literacy programme under way.
Months 7–12 · Extension Ensure everything that exists is within the framework. Complete regularisation; current R6 in all use cases in production; nonconformities managed with time limits; costs per use case; first audit of the framework by the third line in an Enterprise scope.
Months 13–18 · First review (C5) Check progress and adjust direction. Maturity verified with the same questionnaire; transformation index recalculated; thesis reviewed; recalibration of time limits and thresholds; declaration of application where appropriate.

In a Lite scope, the stages may be compressed to reach the declaration between months 6 and 12.

6.2 Path to the core (01 §14.1)

Core rule Questions in document 11 Indicative timing (Lite / Enterprise) Owner
N-12 · C1 and C2 completed with board approval D1.05 Month 3 / month 3–4 Sponsor
N-01 · Inventory with classification, intensity and owner D6.05 Month 6 / month 9 AI Office; AI Risk Owner
N-02 · Use case register with traceability D2.05 Month 3 / month 4 AI Office
N-06 · Roles and bodies with incompatibilities D1.07, D1.08 Month 3 / month 4 AI Committee
N-03, N-04, N-05, N-07, N-08 · Intensity, gates recorded with G3 separately, dual validation and "Yes ◆" D2.06 Month 4 / month 6 AI Office
N-09, N-10 · Value hypothesis, classification and risk register — Month 4 / month 6 AI Office; AI Risk Owner
N-11 · Tested rollback and current continuity review in production; regularisation D4.07 Month 9 / month 12–15 Operations owners
N-13 · Measurement rules and board dashboard D7.05, D7.06 Month 6 / month 9–12 Management control; AI Office
N-14 · Nonconformities with the process in 01 §12 D6.07 Month 6 / month 9 AI Risk Owner; audit

The declaration is based on a verified assessment with all of those questions answered "Yes", on the audit of the declaration, which also checks the rules without a question (38 §11.2), and on regularisation within the time limit (document 11, section 7.3).


07Minimum roles in a small organisation

SEVEN-G does not require new structures to be created. In a small organisation, with a Lite scope, the following allocation is sufficient, provided that the incompatibilities in 01 §8.2 are respected:

Role or body Who can take it on Condition
Board or board committee The board or its audit or risk committee. AI as a recurring item, at least quarterly.
AI Committee Management committee with an extended mandate. Monthly session with its own AI agenda.
AI Office One person with part-time dedication (for example, from strategy, transformation or management control). Cannot verify use cases in which they take part.
Sponsor Head of the area that obtains the value. In Lite, may combine the product, technical and operations roles.
Product, Technical and Operations Owners People from the area or the supplier, with an internal owner. Compatible with each other.
AI Risk Owner Head of compliance, risk or security who does not take part in the construction. Incompatible with the sponsor and with whoever builds.
AI Auditor Internal audit or external auditor. In Lite, may be the same person as the AI Risk Owner. In Enterprise use cases, must be different from the AI Risk Owner: if there is no other person, an external auditor.

Practical minimum: three different people —whoever drives and builds, whoever controls risks and verifies in Lite, and the AI Office—, plus an external auditor for Enterprise use cases.


08Common mistakes

Mistake Consequence How to avoid it
Starting by buying or building tools. Empty registers and technical discussion instead of decisions. Spreadsheet with the model in 03 until the process is working.
Diagnosis by self-assessment. Inflated maturity that does not withstand the first audit. Verified assessment with sampling (document 11).
Creating a parallel governance structure. Duplicated committees and internal rejection. Extend the mandate of existing bodies (01 §8.3).
Applying Enterprise to everything. Slowness and flight towards unauthorised use. Intensity by use case with the criteria in 01 §9.
General AI moratorium during implementation. Loss of support and of opportunities. Stop only what the diagnosis flags as unacceptable risk.
Not reserving the board session from the outset. C2 not approved and portfolio without direction. Reservation in week 1.
Forgetting corporate use and unauthorised use. Partial inventory and invisible risk. Census from procurement, licences and security in week 2.
Documenting after the fact to "comply". Major nonconformity and loss of credibility. Regularisation documentation identified and dated.
Adding released capacity as savings. Inflated value presented to the board. Measurement rules from month 1 (rule 3).
Prioritising everything by immediate return. No Transform bet reaches production. Ambition lanes with their own envelopes (document 14).
AI Auditor dependent on the sponsor. Verification without independence. Third line or external auditor.
Open-ended regularisation time limits. Legacy systems outside the framework indefinitely. Time limits approved in C2 and tracked by the committee.
Presenting implementation as certification. Mistaken expectations on the part of the board and third parties. Declaration of application with its perimeter; audit of the framework separately.

09Implementation indicators

The targets are indicative and are set by the company in its plan.

Indicator Definition 90-day target 12-month target Source
Inventory coverage Areas in the perimeter with a completeness statement ÷ total. 100 % 100 % reviewed during the year T02
New use cases with G0 prior to spending New use cases with G0 before the first expenditure ÷ new use cases. 100 % from week 13 100 % T01
Systems with Enterprise criteria classified Classified ÷ systems with Enterprise criteria. All with classification or date 100 % T02
Regularisation Use cases in production regularised ÷ total predating the framework. Plan approved 100 % T01
Roles without incompatibilities Active use cases without incompatibilities ÷ total. 100 % 100 % T01
Gate decision time Median against the reference time limit (03 §3.6). — Within the time limit T01
Current R6 Use cases in production with a current R6 ÷ total. — 100 % T01
Amounts with status Amounts with formula and status ÷ amounts reported. 100 % in the C1 report 100 % T12
Proportion of validated value Validated value ÷ total value reported. Baseline Target set in C2 T12, T17
Overdue nonconformities Open with an expired time limit. Baseline 0 critical; major ones decreasing T08
AI literacy Staff who use or oversee AI trained ÷ total. Programme approved Target set in C2 Training record (P45)
Core rules (01 §14.1) Rules substantiated ÷ 14. At least 4 14 in Lite; progress according to the roadmap in Enterprise T15

10Associated tools and templates

Period Tools Templates
Month 1 T23 (starting point and journey); T01, T02, T04 (inventory and register); T15 (maturity); T14 (index); T16 (sphere map); T12 (current value). P32, P33, P34, P05
Month 2 T06 (risks); T07 (regulatory classification); T05 (ambition); T19 (thesis and appetite). P35, P43, P06, P07, P11, P12, P31
Month 3 T03 (gates); T08 (nonconformities); T17 (dashboard); T18 (recommendations); T01 and T16 (portfolio). P36, P38, P39, P40, P41, P03, P04, P28, P29
Months 4–18 All of the above; T09, T10, T11, T13, T20, T21, T22 as the portfolio progresses. P01–P31 according to the phase of each use case; P42 and P67 every quarter; P37 in C5; the rest of P32–P74 when applicable

Tools without an application of their own are applied with the template or document indicated in the catalogue in 03. A company that prefers not to use T01 may keep the register in a spreadsheet with the fields of the data model in 03 §4.


Document Relationship
00 · What SEVEN-G is Overview, first implementation and measurement rules.
01 · Foundational methodology Corporate cycle (§5), first implementation (§5.3), roles (§8), intensity (§9), nonconformities (§12) and declaration of application (§14).
03 · Tools and use case register Register, data model, reference time limits and tool catalogue.
10, 12 and 13 Sphere map, transformation index, thesis and risk appetite.
11 · Maturity model Month 1 diagnosis and substantiation of 01 §14.
14 · Portfolio management First portfolio and regularisation.
21, 22, 30, 31, 33, 34, 37, 40, 60, 62 Content of the month 3 governance structure.
95 · Local data and self-hosting Where the tools' data stays and how to host the site within the company.
96 · Starting points and implementation journey Order of this guide's milestones according to the AI and governance the company already has; tool T23.
91 · Guide for consultants External support for the implementation.

12Version control

Version Date Changes
0.1 16-09-2026 First version. Defines the company-level Lite or Enterprise implementation scope, the prerequisites, the week-by-week 90-day plan, regularisation, the 6- to 18-month roadmap up to 01 §14, minimum roles, common mistakes and implementation indicators.
0.1 19-09-2026 Size does not determine the scope (2.1); a single Transform bet does not require an Enterprise scope (2.2); minimum path in a Lite scope (2.4); references to pending documents or tools removed.
0.1 19-09-2026 The minimum path (2.4) refers to the obligation matrix (document 94), to the "The essentials" box of each document and to the course.
0.1 28-09-2026 Reference to document 96 (starting point and implementation journey) in §1, §5, §10 and §11; tool T23 in month 1.
0.2 01-10-2026 Path to the SEVEN-G core (section 6.2) and implementation indicator on the fourteen rules (section 9); equivalences of corporate evidence in week 10 (21 §4.3).
0.3 01-10-2026 Express use cases in the minimum path (section 2.4).

External sources cited

Links to the official or primary source, checked before publication. Always verify the version in force on the date of use.