Template P36 · 19-09-2026

Template P36 · C3 portfolio plan

C3 portfolio plan

Turns the C2 decision into an executable portfolio: envelopes by lane, prioritisation with the six criteria, capacity of scarce profiles, portfolio and concentration limits, calendar, programme traffic light and regularisation plan for existing systems.

Fernando García VarelaVersion 0.1 (working draft)19-09-2026Draft for review

Why it matters. An approved thesis changes nothing if the portfolio is still decided by whoever pushes hardest or by immediate return. The portfolio plan makes visible the criteria and weights used to rank each lane, how much scarce capacity there really is, which risk limits cannot be exceeded and by when the systems that already existed are brought into the framework. Without it, Transform bets compete with optimisations and lose, risk concentration is not seen and regularisation remains open indefinitely.

01Instructions for use

Aspect Guidance
When it is used In C3: in the first implementation, in weeks 11–12 (90 §4.4); thereafter, every year after C2 or C5. It is updated at each quarterly portfolio review (14 §7.2).
Who completes it The AI Office prepares it; management control provides amounts and consumption; the AI Risk Owner provides limits and concentration; sponsors provide the entry records.
Who verifies it The AI Office checks the calculation and the second line the risk limits; the AI Auditor reviews the application of the method by sampling (Enterprise).
Who decides or approves The AI Committee. The board approves Transform use cases and any transfer out of their envelope (14 §2.1).
Corporate cycle stage C3 · Portfolio, with monitoring in C4. Inputs: P33 (C1) and P35 (C2).
Tools T01 (entry record, scoring, lanes, tranches, alerts, "Programme" and "Regularisation" tags), T16 (balance by sphere), T22 (retirements), T06 (risk concentration).
Reference document Document 14 (full method); 01 §5.1; 90 §4.4 and §5.
Lite versus Enterprise Both scopes use the plan. Blocks marked (Enterprise) may be omitted in a Lite scope, with justification.

Completion rules:


02Identification

Field Content Guidance
Document code
Company or group In the examples, always fictitious.
Financial year or portfolio period
Reference C2 decision Version of P35 and DEC-AAAA-NNN.
Reference C1 report Version of P33.
C2 return horizon (years) For the multiple in section 4.
Date of AI Committee approval Reference to the minutes.
Plan version Incremented at each quarterly review with changes.

03Envelopes by lane and budget

Amounts approved in the C2 framework budget (P35, section 11) and their C3 structure (14 §6.1). Committed recurring cost is reserved first.

Item Approved in C2 Committed Available C2 band (% of portfolio cost) Remarks
Committed recurring cost —
Optimise envelope (tranches 2 and 3)
Augment envelope (tranches 2 and 3, including each use case's adoption)
Staged Transform envelope Only stages approved by the board.
Enablement (data, platform, spheres 08 and 09) —
Adoption and training not charged to use cases —
Contingency — Includes the discovery reserve (tranche 1, phases 0–3), the retirement and regularisation reserve and approved deviations (14 §6.1).
Total

04Prioritisation

4.1 Criteria and weights

Four-step method in 14 §4.1: eliminatory filters · assignment to the confirmed lane · scoring · allocation of budget and capacity. Weights in 14 §4.2 (the company may adjust them in C2 and declares them here).

Criterion Optimise Augment Transform Company weights, if different
Additional net value per euro 40 30 15
Fit with the thesis 15 15 25
Contribution to ambition per sphere 5 10 15
Risk 15 15 15
Data dependency 15 15 15
Capacity 10 15 15
Total 100 100 100 100

Score (0–100) = Σ (weight × criterion score) ÷ 5. Scales from 1 to 5 in 14 §4.3.

Spreadsheet formulas (illustrative columns: C = additional net value per euro, H = horizon in years, D to I = scores for the six criteria, weights in row 2):

4.2 Eliminatory filters

They are recorded with a reason and do not enter prioritisation (14 §3.3 and §4.1).

Use case (IA-AAAA-NNN) Filter Treatment
Prohibited practice · Duplicate · Does not require AI · Outside the appetite · Transform without senior management sponsorship · Critical residual risk without board approval

4.3 Prioritisation table by lane

One table per lane: Optimise, Augment and Transform.

Lane: ______

Use case Additional net value per euro Multiple Net Thesis Ambition Risk Data Capacity Score Rank Change of order and justification
(illustrative example, Optimise, 2-year horizon) IA-2026-014 Complaint classification 1.6 3.2 5 4 3 5 4 4 90 1 —

In Transform, additional net value per euro is calculated and shown, but it is not decisive on its own; without learning milestones, a cap per stage and stop criteria, the proposal does not enter (14 §4.4, rules 2 and 7).

4.4 Allocation by tranche

Use case Lane Tranche (1 · 2 · 3 · Scaling · Transform stage) Amount Released after Status (Pending · Released · Consumed)

05Capacity

5.1 Capacity plan for scarce profiles

The AI Office maintains the plan (14 §6.3). Units: full-time equivalents per quarter.

Profile Available Demand from the prioritised portfolio Gap Measure (hire, train, supplier, postpone) Owner Date
Technical owners
Data
Risk
AI Auditor
Security
Adoption
Gate verification and decision Decision time against the reference time limit (03 §3.6).

5.2 Limit on simultaneous use cases

Field Content Guidance
Limit on use cases in phases 3 to 5 Once the limit is exceeded, no new use cases enter phase 4 until one passes G5 or is stopped.
Use cases currently in phases 3 to 5

06Portfolio and concentration limits

6.1 Portfolio risk limits

They translate the C2 appetite (14 §5.2). Exceeding a limit does not stop use cases under way, but it prevents new ones from entering the affected category.

Limit Value set Current value Status (Within · Exceeded) Measure or escalation
Use cases in production with accepted High residual risk
High regulatory risk systems simultaneously in phases 4–5
A2 or A3 agents in production (requires level 3 in D4 and D6)
Investment in systems with direct exposure without independent assessment

6.2 Concentration and supplier dependency (Enterprise)

Quarterly analysis (14 §9). N3 suppliers must have an exit plan.

Type What is measured Warning signal set in C2 Current situation Measure
Supplier
Base model
Data
People
Typical risk (RT-XXX-NN)
Sphere or area

6.3 Ambition balance

Lane C2 band Current proportion of cost Deviation (points) Quarters outside the band Action (14 §5.1)
Optimise
Augment
Transform

The ambition mix by phase is also reviewed (03 §3.5): a portfolio that is balanced in phase 1 but with all its Transform bets halted before G5 is not balanced.


07Review calendar

Moment What is reviewed (14 §2.2 and §7) Dates Owner
Annual (C3) Construction or renewal of the portfolio. AI Committee
Quarterly Balance, concentration, programmes, retirements, budget; report to the board in C4. AI Committee
Monthly Funnel, stalled use cases, expired conditions, holds and new entries. AI Committee
Ongoing Registrations, T01 alerts and preparation of information. — AI Office

08Programme traffic light

Rules and initial thresholds in 14 §12: the programme's colour is the worst of its axes; no data is grey and the programme cannot be green; every programme in red presents a plan at the next monthly review.

Programme Schedule Cost Value Risk Governance Adoption Programme colour Previous quarter's colour Plan or decision
(illustrative example) Customer service Green Amber Grey (no data) Green Green Amber Amber Green Measure value before the next monthly review

09Regularisation plan

Systems and use cases pre-dating the framework (14 §11; 90 §5). First those that meet any Enterprise criterion. Reference time limit: six months from C2 approval for those with Enterprise criteria; 12 months for the rest, unless other time limits are approved in C2.

Code (IA- · SIA-) Name Actual status (Idea · Pilot · Under construction · In production · Corporate use · Unauthorised use) Enterprise criteria Order Treatment Minimum evidence Time limit Owner Review date Outcome
(illustrative example) SIA-2026-004 Enquiries assistant In production Direct exposure 1 Review equivalent to G7 P31, P03, P04, P11, P12, P28, P24, P25, P19 6 months from C2 Head of customer service 15-03-2027 Pending

Rules (14 §11.2): the scope is not extended during regularisation; a use case in production that has not been regularised when the time limit expires is a major nonconformity and, if it meets Enterprise criteria without a regulatory classification, a critical one. Unauthorised use is regularised as a nonconformity: authorise, replace or block.


10Quality criteria

# Check Status
1 The portfolio is prioritised with a documented method that uses additional net value per euro and ambition balance, approved by the committee (question D2.07 in document 11). Met · Not met · Not applicable · Pending
2 Each lane has its envelope and use cases compete only within it; there are no transfers out of the Transform envelope without board approval.
3 The scores can be reproduced with the formula; "no data" entries are recorded as such.
4 Changes to the order have a recorded written justification.
5 There is a capacity plan for scarce profiles and a limit on simultaneous use cases in phases 3 to 5.
6 Portfolio and concentration limits have a set value and a current situation.
7 The regularisation plan has time limits, owners and an order by risk (90 §4.5, criterion 8).
8 The committee reviews the funnel monthly and the balance quarterly, with recorded decisions (question D2.09).

11Approval and verification

Function Role in SEVEN-G Name and position Date Signature or reference
Prepares AI Office
Provides amounts and consumption Management control
Provides limits and concentration AI Risk Owner (second line)
Verifies the method (Enterprise) AI Auditor
Approves the portfolio AI Committee Reference to the minutes
Approves Transform use cases and transfers out of their envelope Board DEC-AAAA-NNN

Segregation of duties: a committee member who sponsors a use case abstains from its prioritisation and does not count towards the quorum for that item (30 §3.3).


12Version control

Completed document

Version Date Author Changes

Template

Version Date Changes
0.1 19-09-2026 First version. Covers the C3 outputs in document 14: envelopes, prioritisation with spreadsheet formulas, capacity, limits and concentration, balance, calendar, programme traffic light and regularisation plan (14 §11; 90 §5).