SEVEN-G
Document 14 · 16-09-2026

Document 14 · Portfolio management

Portfolio management

How the company's AI use cases are selected, prioritised, balanced, reviewed and retired

Fernando García VarelaVersion 0.2 (working draft)16-09-2026Draft for review
3ambition lanes with their own budget
6prioritisation criteria
10steps in the retirement procedure
6programme traffic-light axes

01Purpose and scope

This document develops stage C3 · Portfolio of the corporate cycle (01 §5.1) and ongoing portfolio management in C4 · Oversight. It defines how use cases enter, how they are prioritised and funded, how the balance of ambition and risk is maintained, how the portfolio is reviewed, how stalled use cases are handled, how a use case is retired and how use cases that pre-date the adoption of the framework are regularised.

It applies to all use cases in the register (T01): in-house use cases, third-party AI embedded in processes and corporate use of general-purpose AI that meets any Enterprise criterion (01 §1.2). The main tools are T01 · Use case register, T16 · Portfolio sphere map and T22 · Retirement manager.

This document does not constitute legal advice.

1.1 Portfolio management principles

  1. The portfolio executes the thesis. What is funded is what fits the AI thesis, the ambition per sphere and the risk appetite approved in C2.
  2. Each ambition competes with its peers. A transformation bet does not compete for the same budget or on the same criteria as an optimisation.
  3. Funding is staged. Money is released gate by gate; no one receives the full budget on entry.
  4. Finish before starting. Capacity is allocated first to advanced use cases that meet their criteria.
  5. Risk adds up. The portfolio has concentration limits, in addition to the limits of each use case (principle 5 in 01 §3).
  6. Retiring is managing. A planned retirement frees up resources and reduces risk; it is not a failure of the team.

02Stage C3 · Portfolio

2.1 Inputs, outputs and owners

Element Content
Inputs from C1 Inventory, maturity (document 11), transformation index (12), current validated value and cost.
Inputs from C2 AI thesis, ambition per sphere, risk appetite, framework budget, return horizon, Enterprise investment threshold, reference time limits per phase and concentration limits (document 13).
Mandatory outputs (01 §5.1) Prioritised portfolio with ambition level, sphere, intensity, budget and owners; retirement criteria; available capacity.
Outputs of this document Budget envelopes per lane; prioritisation table; capacity plan; concentration limits applied; regularisation plan; review calendar. They are documented with the C3 portfolio plan (P36).
Owner AI Committee, with preparation by the AI Office.
Approves AI Committee. The board approves Transform use cases and any transfer out of their envelope.

2.2 Calendar

Moment What is done Who
Annual (C3) Building or renewing the portfolio after C2 or C5: envelopes, full prioritisation, capacity, limits. AI Committee; board for Transform
Quarterly Review of balance, concentration, programmes and retirements; report to the board in C4. AI Committee
Monthly Monitoring of the funnel, stalled use cases, expired conditions, holds and new entries. AI Committee
Continuous Registration of use cases, T01 alerts, preparation of information. AI Office

2.3 Responsibilities

A accountable · R responsible · C consulted · I informed.

Activity Board AI Committee AI Office Sponsor AI Risk Owner Management control
Envelopes per lane A R C I C C
Prioritisation and allocation I A R C C C
Approval of Transform A R C R C I
Monthly and quarterly review I A R C C C
Concentration limits I A R I R I
Retirements I A (Enterprise) R A (Lite) C C
Regularisation I A R R C I

03Entry of use cases into the portfolio

3.1 Channels

Use cases may come from business areas, from challenges set by the board or management, from the AI Office or from supplier proposals. Every use case needs a business sponsor: a supplier proposal without an internal sponsor does not enter. Document 54, section 5, sets out the eight sources use cases come from, the typical bias of each and what each lacks before entering.

3.2 Minimum entry record

To move from Registered to phase 0 (03 §3.2), the use case provides:

Field Requirement
Understandable description What it is and what it is used for, without jargon (rule 10; P31).
AI Sponsor and AI Product Owner Appointed and without incompatibilities (01 §8.2).
Proposed sphere and ambition Using the five questions in 00 §5.2 (T05).
Order of magnitude of value With formula, marked as estimated (rule 4).
Investment up to G3 Amount of the discovery and feasibility tranche.
Fit with the thesis Thesis objective to which it contributes.
Foreseeable Enterprise criteria Intensity questionnaire (T04).

3.3 Preliminary filters

The following do not enter the portfolio, and are recorded with the reason: practices prohibited by regulation; use cases that duplicate an existing one (they are merged); those that do not require AI (they are referred to the alternative); those that fall outside the approved risk appetite; and Transform use cases without senior management sponsorship.

3.4 Entry windows


04Prioritisation criteria

4.1 Four-step method

  1. Eliminatory filters (section 3.3 and Critical residual risk without board approval).
  2. Assignment to the confirmed ambition lane: Optimise, Augment or Transform.
  3. Scoring with six criteria and weights specific to each lane (sections 4.2 and 4.3).
  4. Allocation of budget and capacity in order of score within each lane, with a check on balance and concentration (sections 5 and 6).

The committee may alter the resulting order with a written justification recorded in T01. Changes affecting the Transform lane are reported to the board.

4.2 Criteria and weights

The additional net value per euro (expected additional annual net value ÷ additional investment required; rule 9) is the main criterion in Optimise and Augment. In Transform it is always calculated and shown, but it is not decisive on its own (01 §7.6).

Criterion What it assesses Optimise Augment Transform
Additional net value per euro Expected return on the additional investment within the C2 horizon. 40 30 15
Fit with the thesis Contribution to an explicit objective of the AI thesis. 15 15 25
Contribution to ambition per sphere Whether it fills a gap between the ambition set per sphere and the actual portfolio. 5 10 15
Risk Expected residual risk level (document 33). 15 15 15
Data dependency Availability, quality and legal basis of the data required. 15 15 15
Capacity Team, supplier and adoption capacity of the receiving area. 10 15 15
Total 100 100 100

Use case score (0–100) = Σ (weight × criterion score) ÷ 5.

4.3 Scoring scales

All scales run from 1 to 5. A criterion with no data scores 0 and is shown as "no data" (rule 8); a use case with no data on additional net value per euro cannot pass G2.

Additional net value per euro. The multiple over the horizon is used = additional net value per euro × C2 return horizon in years. A multiple of 1 means that the additional investment is recovered within the horizon, undiscounted. It is a prioritisation criterion, not a feasibility criterion: economic feasibility at G3 is decided solely by NPV ≥ 0 with the horizon and rate set in C2 (document 40, section 8.3; 01 §7.6).

Multiple over the horizon Score
3 or more 5
From 2 to less than 3 4
From 1.5 to less than 2 3
From 1 to less than 1.5 2
Less than 1 1. Does not by itself prevent passing G3: NPV ≥ 0 applies at G3 (document 40).

Initial thresholds, to be calibrated. If after G2 the amount is still only estimated, with no measured baseline, the score for this criterion cannot exceed 3.

Score Fit with the thesis Contribution to ambition Expected residual risk Data dependency Capacity
5 Explicit thesis objective in a priority sphere. Fills a gap: sphere with a set ambition and no use cases at that level. Low Data available, quality verified and legal basis confirmed. Team and supplier assigned; receiving area with adoption capacity.
4 Explicit objective in a non-priority sphere. Reinforces a level below its target. — Available with minor adjustments. Team assigned; supplier being selected.
3 Permitted sphere without an explicit objective. Neutral. Medium Require planned preparation within phase 3. Capacity available in the following quarter.
2 Indirect fit. Adds to a level already at its target. — Not available, but obtainable with identified data work. Capacity available in two quarters or dependent on hiring.
1 No fit; requires justification from the sponsor. Increases concentration in a level already above its target. High Non-existent or with a doubtful legal basis. No capacity identified within 12 months.

Critical residual risk is not scored: it is an eliminatory filter unless there is exceptional board approval within the risk appetite (document 33).

4.4 Rules to prevent return from blocking transformation

  1. Separate envelopes. C2 sets the proportion of the framework budget for each lane. Use cases compete only within their lane.
  2. Own criteria. Transform use cases are decided using the criteria in 01 §7.6: learning milestones, investment cap per stage, stop criteria and documented option value; not with a threshold of additional net value per euro.
  3. No silent transfers. The Transform envelope is not reallocated to other lanes without board approval. The unused envelope is reported to the board, because it is a signal of the transformation index (signal 1).
  4. Stopping on pre-agreed criteria. A Transform bet is stopped only on its stop criteria or on grounds of risk, not by being compared mid-stage with optimisations offering immediate return.
  5. Market evidence at the right time. Transform is not required to have validated value before G5; at G5 it is required to provide market or customer evidence.

And, conversely, to prevent "Transform" from becoming a refuge:

  1. Verified classification. A use case presented as Transform that answers no to questions 1 to 4 in 00 §5.2 is reclassified and changes lane.
  2. No milestones, no bet. A Transform proposal without learning milestones, a cap per stage and stop criteria does not enter prioritisation.

4.5 Illustrative example

Illustrative data. Optimise lane; C2 return horizon: 2 years.

Use case Additional net value per euro Multiple Net Thesis Ambition Risk Data Capacity Score
IA-2026-014 Complaint classification 1.6 3.2 5 4 3 5 4 4 90
IA-2026-021 Invoice reconciliation 0.9 1.8 3 5 3 5 5 3 78
IA-2026-009 Network incident forecasting 1.2 2.4 4 3 3 3 2 2 63

Calculation for IA-2026-014: (40 × 5 + 15 × 4 + 5 × 3 + 15 × 5 + 15 × 4 + 10 × 4) ÷ 5 = 450 ÷ 5 = 90. IA-2026-009 has a better net value than IA-2026-021, but ranks behind it on risk, data and capacity: the score sets the order, and negative net value or no data is detected separately.


05Balance of ambition and risk

5.1 Ambition balance

C2 sets the target distribution of investment across lanes and the ambition per sphere. SEVEN-G does not impose proportions: they depend on the thesis. The portfolio is compared with the target at each quarterly review using the spheres × ambition levels map (T16), with investment, recurring cost and value per cell.

Deviation from the C2 target Reading Action
Up to 10 percentage points per lane Within tolerance. Monitoring.
More than 10 points for one quarter Imbalance. The committee proposes measures: new entries, acceleration or reallocation within the rules in 4.4.
More than 10 points for two quarters, or an empty Transform lane with a set ambition Persistent imbalance. The board is informed and confirms the ambition or modifies it in C2.

Proportions are measured on committed investment and also on the ambition mix by phase (03 §3.5): a portfolio that is balanced in phase 1 but with all its Transform bets halted before G5 is not balanced.

5.2 Risk balance

The C2 risk appetite is translated into portfolio limits, which the committee reviews quarterly. The values are set by each company; for reference:

Limit Example wording
High residual risk Maximum number of use cases in production with accepted High residual risk.
High regulatory risk systems Maximum number simultaneously in phases 4–5, according to control capacity.
Autonomy Agents with A2 or A3 autonomy in production only with level 3 in D4 and D6 (document 11).
Direct exposure Maximum proportion of investment in systems with direct exposure without independent assessment.
Suppliers See section 9.

Exceeding a limit does not stop use cases under way, but it prevents new ones from entering the affected category until the committee approves a measure or the board modifies the appetite.


06Capacity and staged budget

6.1 Structure of the framework budget

Item Content
Committed recurring cost Operating cost of use cases in production. It is reserved first: each go-live reduces the budget available for new use cases in subsequent years.
Optimise envelope Tranches 2 and 3 of its lane.
Augment envelope Tranches 2 and 3 of its lane, including the adoption specific to each use case.
Staged Transform envelope Stages approved by the board, each with its cap per stage.
Enablement Data, common platform, governance and compliance, including use cases in spheres 08 and 09.
Adoption and training AI literacy, role-based training and change management not charged to use cases.
Contingency Includes the discovery reserve (tranche 1 of all use cases, phases 0–3, before their lane is confirmed), the retirement reserve (retirements and regularisation) and approved deviations. Allocated by the AI Committee with a record.

The items are the seven envelopes of the framework budget approved by the board in C2 (13 §12); this section sets how the portfolio uses them. The portfolio plan records them in P36 §3.

6.2 Funding tranches

Tranche Phases funded Released after Limit
1 · Discovery and feasibility 0–3 G0 Amount declared in the entry record.
2 · Design and delivery 4–5 G3 Build and pilot cost from the feasibility assessment (P10).
3 · Operation 6 G5 Annual recurring cost; renewed at each R6.
Scaling New phase 0 G7 with a Scale outcome New cycle with its own prioritisation.

In Transform, each approved stage is a tranche with its learning milestone; the next stage is not released until the milestone has been met. A deviation of more than 10% over the approved tranche requires approval from the body that decided the gate.

The tranches of each use case are recorded in T01, in the realisation plan (plan_realizacion.tramos), with their date, amount, the gate that releases them and their pass condition, the milestone that must be met to release them (document 43 §4.1). Only investments are recorded as tranches: 1 · discovery and feasibility, 2 · design and delivery, scaling and, in Transform, each stage. Tranche 3 · operation is not recorded as a tranche: it is the recurring cost, which the realisation curve already deducts. The board dashboard (T17) lists the pending tranches, flags those without a pass condition and shows the annual net value each tranche unlocks per euro invested (F3 of the tranche, document 40 rule 9).

6.3 Capacity


07Monthly and quarterly review

7.1 Monthly AI Committee review

Item Source Possible decision
New entries and Enterprise gates T01, T03 Admit, prioritise, decide gates.
Stalled use cases, expired conditions and holds T01 alerts Section 8.
Cost and value deviations T12, T13 Conditions, early R6.
Incidents and major or critical nonconformities T08 Containment, stop, retirement.
Funnel metrics: time in phase, decision time, conversion T01 Measures on bottlenecks.

7.2 Quarterly portfolio review

Item Content Result
Balance T16 map; ambition mix by phase; deviation from C2. Measures in section 5.1.
Risk and concentration Limits in sections 5.2 and 9. Measures or escalation to the board.
Value Value by phase, realised value against hypothesis, validated proportion, weighted value if there is a track record. Review of priorities.
Programmes Traffic light in section 12. Recovery plans.
Retirements Proposed retirements and those under way. G7 decisions.
Budget and capacity Consumption by tranche and lane; capacity plan. Reallocations within the rules in 4.4.
Report to the board (C4) Summary in the response format of documents 60 and 61. Recorded recommendations (T18).

08Stalled use cases, expired conditions and use cases on hold

The definitions and metrics are those in 03 §3.5 and §3.6.

Situation Treatment Time limit
Stalled (exceeds the reference time limit for its phase) The AI Product Owner explains the cause and the plan. The committee decides: recovery plan with a date; new justified time limit (only once per phase); move to On hold with a reason; early gate; or stop. Explanation within 5 working days; decision at the next monthly meeting.
Second stall in the same phase Early gate with the option of stopping explicitly considered. Next monthly meeting.
Expired condition The gate outcome becomes Iterate (01 §7.4, rule 4). If the condition affects a significant control, a major nonconformity is raised (01 §12). Automatic on expiry.
On hold Requires a coded reason and an expected resumption date. Time on hold does not count as time in phase, but the allocated capacity is released. Review at each monthly meeting.
Prolonged hold (more than 90 days or two postponements) The committee decides to resume with a firm date or to stop. The unspent tranche budget returns to its budget item. Next monthly meeting.

09Risk concentration and supplier dependency

The committee analyses quarterly whether several use cases could fail for the same cause.

Type of concentration What is measured Warning signal (to be set in C2)
Supplier Proportion of use cases in production, recurring cost and critical functions that depend on the same supplier. One supplier supports several critical functions or exceeds the set proportion.
Foundation model Use cases that depend on the same general-purpose AI model or its version. Announced change or withdrawal of the model affecting several use cases.
Data Use cases that depend on the same dataset or knowledge source. Source with quality issues or a legal basis under review.
People Use cases that depend on the same key people. One person is indispensable to several use cases.
Typical risk High residual risks with the same RT-XXX-NN code. Same High risk in several use cases.
Sphere or area Concentrated investment and exposure. Deviation from the ambition per sphere.

Measures. Suppliers with requirement level N3 (document 36) must have a tested exit plan or, at least, a documented one with an estimated cost, which is incorporated into the use case's net value. In entities subject to DORA, ICT services supporting critical or important functions require exit strategies (Article 28 of Regulation (EU) 2022/2554). A significant change in the supplier or the foundation model triggers an extraordinary R6 of the affected use cases.


10Retirement procedure

Retirement is a G7 outcome (01 §6.9 and §7.3). Every retirement must record the date, reason, deciding body, replacement if any, treatment of data and models and communication to those affected (01 §6.9). This procedure also applies to partial retirement (reduction in scope, users or functions) and, with the adaptations in 10.10, to corporate use of AI.

10.1 Retirement criteria

Trigger Indicative criterion Coded reason (03 §3.3)
Value not sustained Realised value below the hypothesis success threshold in two consecutive R6 reviews. Hypothesis refuted
Cost exceeds value Negative annual net value over two R6 reviews without a credible correction plan. Cost exceeds value
Risk Residual risk outside the appetite, repeated S1 or S2 incidents or a critical nonconformity with no viable remedy. Unacceptable risk
Regulation Regulatory change that prohibits the use or imposes obligations that cannot be met in time. Regulation
Adoption Actual use persistently below forecast after the measures in the adoption plan. No adoption
Better alternative Another solution, with or without AI, delivers more net value or less risk. Replaced by another solution
Technology or supplier End of support, withdrawal of the foundation model or unacceptable contractual change. Technically unfeasible
Strategy The revised thesis no longer includes the sphere or objective. Change in strategic priority

When risk so requires, the use case is halted immediately using the kill switch or the rollback plan (P19) and the formal G7 is held afterwards, within a maximum of 10 working days.

10.2 Owners

Role Responsibility in the retirement
AI Sponsor Proposes or accepts the retirement; decides in Lite; is accountable for the replacement and the financial close.
AI Committee Decides in Enterprise; informs the board when a Transform use case or one supporting a critical function is retired.
AI Product Owner Draws up the retirement plan; leads the transition and communication to users.
AI Technical Owner Deactivation, dismantling of integrations, archiving of models and documentation.
AI Operations Owner Carries out the deactivation, revokes identities and permissions, monitors until closure.
AI Risk Owner Regulatory and retention obligations; clearance of the plan.
Data protection and legal counsel Processing of personal data; contractual close-out with suppliers.
AI Auditor or AI Office Verifies closure (auditor in Enterprise, office in Lite).
AI Office Recording in T22, updating of T01 and T02, consolidation of lessons.

10.3 Flow

Retirement procedure
Ten steps from proposal to recording
flowchart LR
  A["1. Proposal"] --> B{"2. G7"}
  B -->|"Scale or Iterate"| X["Remains in portfolio"]
  B -->|"Retire"| C["3. Retirement plan"]
  C --> D["4. Replacement and transition"]
  D --> E["5. Communication"]
  E --> F["6. Deactivation"]
  F --> G["7. Data, models and access"]
  G --> H["8. Contractual close-out"]
  H --> I{"9. Closure verification"}
  I -->|"Outstanding items"| G
  I -->|"Conformant"| J["10. Lessons and recording"]
  classDef ok fill:#d9ebe0,stroke:#0d7680,color:#1a1817
  classDef med fill:#f2dfce,stroke:#0f5499,color:#1a1817
  classDef ko fill:#f3d3da,stroke:#990f3d,color:#1a1817
  class J ok
  class B,I med
  class F ko
Source: SEVEN-G

Reference time limits: retirement plan approved within 15 days (Lite) or 30 days (Enterprise) of the decision, in line with the phase 7 time limits (03 §3.6); closure verification within 30 days of deactivation.

10.4 Content of the retirement plan (P30)

Block Content
Decision Use case code, G7 date, body, coded reason, scope (full or partial).
Schedule Change freeze date, parallel running period, deactivation date, closure date.
Replacement Solution that takes over the function, acceptance criteria and capacity required (10.6).
Those affected Users, customers or people affected, areas, suppliers, authorities where applicable.
Data, models and access Treatment of each element (10.5).
Contracts Notice periods, penalties, return or deletion of data by the supplier.
Retirement cost Estimate and budget item (retirement reserve, section 6.1).
Retirement risks Transition risks recorded using the scale in document 33.
Verification Closure checklist and verifier.

10.5 Treatment of data, models and access

Element Treatment
Personal data Erasure or blocking according to the legal basis and retention periods (GDPR, Articles 5(1)(e) and 17); record of the deletion.
Data held by the supplier Return or deletion in accordance with the contract, with a certificate.
Models, versions and configurations Archiving with version and lineage (P16) for as long as there is an obligation to retain documentation or a possibility of claims; thereafter, recorded destruction.
Technical documentation and activity logs Retention in accordance with regulation. The EU AI Act sets, among other things, 10 years for the documentation of providers of high-risk systems (Article 18) and at least six months for automatically generated logs (Articles 19 and 26(6)). Verify that this is in force at the date of consultation (September 2026).
Instructions, knowledge bases and indexes Archiving if they support decisions that may be challenged; otherwise, recorded deletion.
Identities, credentials and permissions of agents and integrations Revocation before or at the same time as deactivation. No identity may remain active.
Decisions made with the system Retention of the traceability needed to handle claims and the rights of individuals.
Inventory and register T02 moves the system to "retired"; T01 moves the use case to Retired with the closure date.

10.6 Replacement and continuity

10.7 Communication

Recipient When Content
Internal users On approval of the plan and before deactivation Dates, alternative, training, support.
Customers or people affected With sufficient notice when there is direct exposure What changes, service channel, rights.
Workers' representatives When required by law or agreements Effect on work.
Suppliers In accordance with contractual notice periods Termination, return or deletion of data.
Authorities If the system was registered or subject to regulatory notification Update in accordance with the applicable regulation.
Committee, board and audit Decision and closure Reason, cost, lessons.

10.8 Lessons learned

Every retirement, and every stop at G3 or later, produces a lessons note with: initial hypothesis; what happened; coded reason; what early signal foreshadowed it and when it was noticed; total investment and cost against realised value; and what change is proposed to entry criteria, templates or thresholds. The AI Office consolidates them by reason and presents them in C5 (P37 §9).

10.9 Retirement register (T22)

Field Content
Identification Code IA-AAAA-NNN, systems affected, full or partial scope.
Decision G7 date, body, decision-maker, verifier, coded reason, reference to P29 and P30.
Plan Planned and actual dates for freeze, parallel running, deactivation and closure.
Replacement Solution, owner, acceptance criteria met.
Data and models Status of each element in 10.5 with evidence.
Access Date of revocation of identities and permissions.
Communication Recipients and dates.
Economics Total investment, recurring cost avoided, retirement cost, cumulative realised value with its status.
Closure Verification date, result, outstanding items.
Lessons Link to the lessons note.

10.10 Corporate use and unauthorised AI

The retirement of an AI tool for corporate use follows steps 3 to 10 with a simplified plan. Detected unauthorised use is regularised as a nonconformity (01 §1.2): authorisation, replacement or blocking; if it is blocked, 10.5 and 10.7 apply.


11Regularisation of use cases pre-dating the framework

Use cases in production prior to the adoption of SEVEN-G must be regularised within the time limit approved in C2, by undergoing a continuity review equivalent to G7 (01 §14).

11.1 Steps

  1. Census. Registration in T01 and T02 of everything that exists, with its actual status: idea, pilot, under construction or in production.
  2. Order by risk. First, those that meet any Enterprise criterion (01 §9.2), in particular high regulatory risk, decisions about people, direct exposure and agents that act; then the rest.
  3. Treatment by status:
Actual status Treatment Possible outcome
In production Review equivalent to G7 with minimum evidence: description (P31), roles (P03), intensity (P04), regulatory classification (P11), risks (P12), realised value with status (P28), manual and monitoring (P24, P25), rollback plan (P19). Continue in production with periodic R6; continue with conditions; iterate; retire.
Under construction It is placed in the phase that corresponds to its actual evidence and must pass the next gate with all the evidence from the previous phases. Continue from that phase; pivot; stop.
Pilot It is assessed at G3 with the pilot results. Continue; iterate; stop.
Idea Ordinary entry (section 3). —
  1. Recording. Each regularised use case carries the free tag "Regularisation" and the date of its review.

11.2 Rules


12Programme traffic light

A programme groups related use cases using the free tag "Programme" (03 §3.3). The traffic light summarises its status for the committee and the board.

12.1 Axes and initial thresholds

Axis Green Amber Red
Schedule No stalled use cases; milestones on schedule. One stalled use case or a milestone delayed by up to one phase reference time limit. Several stalled use cases or a critical milestone with a longer delay.
Cost Deviation over the approved tranches of up to 10%. From 10% to 25%. More than 25% or without approval.
Value Realised value equal to or above 90% of the amount forecast to date, with validated or declared status. From 60% to 90%, or estimated only. Less than 60%, or hypothesis refuted without a decision.
Risk No residual risks outside the appetite and no open S1–S2 incidents. High risk with mitigation on schedule or an S2 incident being managed. Risk outside the appetite, S1 incident or open critical nonconformity.
Governance Gates, R6 and conditions up to date. One expired condition or an R6 delayed by less than one month. Expired major nonconformity, lapsed R6 in Enterprise or system in production without a gate.
Adoption Actual use equal to or above 80% of forecast. From 50% to 80%. Less than 50% after the measures in the plan.

Initial thresholds, to be calibrated in C5.

12.2 Traffic-light rules

  1. Programme colour = worst colour of its axes. One axis in red puts the programme in red.
  2. No data is not green. An axis with no data is shown in grey and the programme cannot be green.
  3. Red requires a plan. Every programme in red presents a recovery plan with an owner and date, or a proposal to stop or retire, at the next monthly review.
  4. Two quarters in red lead the committee to decide explicitly between continuing with a revised plan, reducing scope, stopping or retiring, and the board is informed.
  5. Visible trend. Each traffic light shows the colour for the previous quarter.

13Associated tools and templates

Code Use in this document
T01 · Use case register Entry record, alerts for stalled use cases, holds and conditions, "Programme" and "Regularisation" tags. The prioritisation score, lanes and tranches, the regularisation plan and the programme traffic light are prepared with P36 (C3 portfolio plan), with columns ready for a spreadsheet; the traffic light is presented to the board in P67.
T16 · Portfolio sphere map Ambition balance per sphere with investment, recurring cost and value.
T22 · Retirement manager Retirement plan, replacement, data and models, access, communication, closure verification and retirement register (section 10.9).
T02, T03, T04, T05, T06, T08, T09, T12, T13, T14, T17, T18 Inventory, gates, intensity, ambition, risks, nonconformities, suppliers, value, costs, transformation index, dashboard and recommendations.
P06, P07, P08, P10, P12, P14, P19, P28, P29, P31 Evidence used in entry, prioritisation and review.
P30 · Scale or retirement decision G7 decision, lessons learned and retirement plan.
P36 · C3 portfolio plan Envelopes by lane, prioritisation, capacity, concentration limits, regularisation plan, review calendar and programme traffic light (section 2.1).
P37 · C5 annual review Lessons learned consolidated by reason (section 10.8).

Document Relationship
00 · What SEVEN-G is Value measurement rules (§6) and ambition classification (§5.2).
01 · Foundational methodology C3 (§5.1), phase 7 (§6.9), gate outcomes and rules (§7), principles, declaration of application (§14).
03 · Tools and use case register Statuses, taxonomy, coded reasons, funnel metrics and reference time limits.
10 · Sphere map Ambition per sphere.
11 · Maturity model Dimension D2 and maturity requirements for agents and Transform.
12 · Transformation index Signals affected by the portfolio balance.
13 · AI thesis and risk appetite Envelopes, horizon, limits and time limits used by this document.
33 · Risk methodology Risk scale and typical risks.
36 · Third parties and suppliers Levels N1–N3 and exit plans.
40–43 · Measurement and value Additional net value per euro, costs and benefits realisation.
90 · Implementation guide First portfolio and regularisation.

15Version control

Version Date Changes
0.1 16-09-2026 First version. Develops C3; defines portfolio entry, prioritisation by ambition lanes with six criteria, rules to avoid blocking transformation, balance of ambition and risk, tranche-based budget, monthly and quarterly reviews, treatment of stalled use cases and holds, concentration, full retirement procedure with register, regularisation and programme traffic light.
0.2 28-09-2026 Funding tranches are recorded in T01 (plan_realizacion.tramos) with gate, amount and pass condition, and the board dashboard lists the pending ones with the annual net value each one unlocks per euro (§6.2; D135).

External sources cited

Links to the official or primary source, checked before publication. Always verify the version in force on the date of use.