Template P21 · Delivery report

Delivery report

Records what has been built or integrated against the design approved at G4, at what cost and in what time, and in what state it is handed over to operations.

Fernando García VarelaVersion 0.1 (working draft)16-09-2026Draft for review

01Instructions for use

Aspect Guidance
When it is used Phase 5 (Delivery and validation), on completion of the build or integration and before requesting G5.
Who completes it AI Technical Owner, with the AI Product Owner. If there is a supplier, it provides the information, but the report is signed by the company's AI Technical Owner.
Who verifies it AI Risk Owner under Lite; AI Auditor under Enterprise.
At which gate it is reviewed Go-live. (G5)
Lite versus Enterprise Lite may omit the fields marked (Enterprise).
Relationship P15–P20 (approved design) · P22 Validation and pilot results · P23 Go-live sign-off · P24 Operations manual · P29 G4 decision record (conditions) · documents 42 (Costs) and 53 (Building solutions).

Rules:


02Identification

Field Content Guidance
Use case code IA-AAAA-NNN (T01).
Use case name
AI system(s) Identifier in the inventory (T02).
Version delivered Version of model, prompts and configuration (P16).
Intensity Lite · Enterprise.
Ambition level Optimise · Augment · Transform.
Suppliers involved Name and reference to P14.
Document version
Author Role and name.
Date DD-MM-AAAA.
Document status Draft · Submitted for verification · Verified · Approved · Superseded.

03Delivery summary

Field Content Guidance
What has been delivered In three to five lines, in plain language.
Main differences from the approved design Summary of block 4.
Readiness for go-live Ready · Ready with non-critical outstanding items · Not ready.
Critical outstanding items If any exist, the status cannot be "Ready".

04Scope delivered against the approved design

Status: Delivered as designed · Delivered with changes · Not delivered.

Design element Design evidence Status Changes and justification Does it affect risks, oversight or security? (Yes · No) Approval of the change
Architecture and integrations P15
Data and models P16
Human oversight P17
Security and agent controls P18
Rollback mechanism and kill switch P19
Training and adoption P20
Monitoring and alerts P25
Integration with the supplier's system (illustrative example) P15 Delivered with changes The real-time connection is replaced by an hourly load due to supplier limitations Yes: delay of up to one hour in the input data AI Technical Owner with risk clearance

If a change affects risks, human oversight or security, the corresponding design evidence and the risk register (P12) must be updated before G5.


05Outstanding conditions from previous gates

Status: Met · Not met · Expired.

Condition Originating gate Owner Deadline Status Evidence

06Documentation delivered

Document Delivered (Yes · No · Not applicable) Version Location
Technical documentation of the system
Updated data and model lineage (P16)
User manual
Draft operations manual (P24)
Monitoring and alert configuration (P25)
Incident response plan (P26)
Technical documentation required by regulation for high-risk systems (Enterprise) Reference to the regulatory mapping (document 34).
Supplier documentation and warranties (Enterprise)

07Actual versus planned costs

Amounts in euros. "Planned" is what was approved at G3 (P10) or, if updated, at G4.

Cost category Planned investment Actual investment Planned annual recurring cost Updated annual recurring cost Deviation and explanation
Licences
Model consumption
Compute and infrastructure
Data
Build people — —
Operations people — —
Suppliers and services
Control and compliance
Adoption and training
Total

If the updated recurring cost changes the expected annual net value, it is recalculated in P22 and flagged to the gate decision-maker.


08Timelines

Milestone Planned date Actual date Days of deviation Cause
G4 approval
Start of build
End of build
Start of pilot
Planned G5 request

If phase 5 exceeds the reference time limit approved in C2 (03 §3.6), indicate the periods on hold and the reason.


09Known limitations, technical debt and open risks

# Description Type (Limitation · Technical debt · Open risk) Effect on operation Treatment Owner Date
1 (illustrative example) Retraining requires manual intervention Technical debt Greater dependence on two people Automate before the second R6 AI Technical Owner

10Handover to operations

Check Status (Met · Not met · Not applicable · Pending) Observations
The AI Operations Owner has received and reviewed the documentation.
Operational access, credentials and permissions configured and reviewed.
Alerts connected to the on-call recipients.
Operations staff trained in rollback and the kill switch.
Support agreements with suppliers in force (Enterprise)
AI system inventory updated with the version delivered.

11Quality criteria

Formal G5 criteria in document 21; checklist LV-G5 in document 22.

# Check Status (Met · Not met · Not applicable · Pending)
1 Every design element has a delivery status and changes are justified and approved.
2 Changes affecting risks, oversight or security have updated their evidence.
3 All conditions from previous gates have been met or their expiry has been recorded.
4 Actual costs are shown by category, separating investment and recurring cost.
5 Limitations and open risks have a treatment and an owner.
6 The handover to operations is complete or its outstanding items are not critical.

12Approval and verification

Function Role Name Date Signature or reference
Author AI Technical Owner
Co-author AI Product Owner
Receipt AI Operations Owner
Verifier AI Risk Owner (Lite) · AI Auditor (Enterprise)
Gate decision-maker According to 01 §7.5 (recorded in P29)

Segregation of duties: the verifier is not part of the team that builds.


13Version control

Version Date Changes
0.1 16-09-2026 First version of the template.